| 2007-11-09 11:00:46 | ***** FAILED ***** |
| | |
| | |
| | 1.PLEASE SHOW IN DOCUMENT, HOW DID YOU DETERMINE THE |
| | FIRST FLOOR ELEVATION? PLEASE SHOW IN CALS THAT YOU |
| | CONSIDERED,CENTER LINE OF ROAD , SIDEWALK ELEVATION, |
| | FL BLDG CODE, & FLOOD ZONE AREA OF THIS LOCATION, |
| | PLEASE SHOW ALL THESE IN YOUR DOCUMENT. PLEASEALSO |
| | SHOW IN YOUR CALCULATION THAT YOUR FLOOR ELEVATION IS |
| | HIGHENOUGH TO MEET5, 10, 25, 100 YEAR FLOOD |
| | CALCULATION. FIRST FLOOR ELEVATION SHOULD BE HIGHER |
| | THAN MAX CROWN OF THE ROAD ELEVATION BY 1 FOOT, |
| | ATLEAST. |
| | |
| | 2. PLEASE PROVIDE A COPY OF SFWMD PERMIT,, |
| | |
| | 3. INYOUR WATER QUALITY CALS ON 1ST PAGE, IN |
| | CALCULATION OF % IMPERVIOUSTHERE IS A MINOR ERROR.% |
| | OF IMPERVIOUS SHOULD BE = 1.02/1.91=0.53% IMPERVIOUS |
| | PER SFWMD PROCEDURE.SO,.53X2.5X4.736/12= 0.53 AC-FT |
| | TO BE TREATED. CHANGES AREMARKED IN YOUR CALS. SO, |
| | PLEASE REVISE THIS CALCULATIONS.WE USE SFWMD |
| | CRITERIA.DO YOU KEEP ALL STORM WATER ON SITE??, OR |
| | GOES INTOANY CANAL? PLEASE EXPLAIN. PLEASE ALSO |
| | RESUBMIT GEO-TECH REPORT WITH WATER QUALITY CALS. |
| | |
| | 4. PLEASE SHOW ON THE DRAWING THE SITE AREA, PERVIOUS, |
| | IMPERVIOUS AREAYOU ARE DEVELOPING FOR THIS PROJECT |
| | ONLY ? DO YOU HAVE LAKE? PLEASE MAKE SURE THE AREA YOU |
| | USED IN WATER QUALITY CALS DO MATCH WITH THE AREA YOU |
| | SHOW ON DRAWINGS. |
| | |
| | PLEASE RESPOND EACH ITEM IN DETAIL TO EXPEDITE YOUR |
| | PERMITTING PROCESS |
| | |
| | RASIK CHOKSHI805-6723 |