| 2007-09-28 10:55:18 | ***** FAILED ***** |
| | |
| | |
| | 1. WE COULD NOT FIND THE DRAWINGIN YOUR SUBMITTAL |
| | 1/A-2 FOR DUMPSTER DETAILS,PER MR. CAMERO'S RESPONE |
| | LETTER OF MAY 23. 07. |
| | 2.PLEASE SHOW IN DOCUMENT, HOW DID YOU DETERMINE THE |
| | FIRST FLOOR ELEVATION? PLEASE SHOW IN CALS THAT YOU |
| | CONSIDERED,CENTER LINE OF ROAD , SIDEWALK ELEVATION, |
| | FL BLDG CODE, & FLOOD ZONE AREA OF THIS LOCATION, |
| | PLEASE SHOW ALL THESE IN YOUR DOCUMENT. PLEASEALSO |
| | SHOW IN YOUR CALCULATION THAT YOUR FLOOR ELEVATION IS |
| | HIGHENOUGH TO MEET5, 10, 25, 100 YEAR FLOOD |
| | CALCULATION. SFWMD ALSO CHECK FIRST FLOOR ELEVATION |
| | BEFORE WE APPROVE. |
| | 3. PLEASE PROVIDE A COPY OF SFWMD PERMIT,, |
| | 4. INYOUR WATER QUALITY CALS ON 1ST PAGE, IN |
| | CALCULATION OF % IMPERVIOUSTHERE IS A MINOR ERROR.% |
| | OF IMPERVIOUS SHOULD BE = 1.02/1.91=0.53% IMPERVIOUS |
| | PER SFWMD PROCEDURE.SO,.53X2.5X4.736/12= 0.53 AC-FT |
| | TO BE TREATED. CHANGES ARE MARKED IN YOUR CALS. SO, |
| | PLEASE REVISE THIS CALCULATIONS.WE USE SFWMD |
| | CRITERIA. DETAIL OF CONTROL STRUCTURE ETC . DO YOU KEEP |
| | ALL STORM WATER ON SITE??, OR ANY CANAL? PLEASE |
| | EXPLAIN. PLEASE ALSO RESUBMIT GEO-TECH REPORT WITH |
| | WATER QUALITY CALS. |
| | 5. PLEASE SHOW ON THE DRAWING THE SITE AREA, YOU ARE |
| | DEVELOPING FOR THIS PROJECT ONLY ?ALSO, WHAT IS TOTAL |
| | PERVIOUS,& IMPERVIOUS AREA FOR THIS PROJECT., DO YOU |
| | HAVE LAKE? PLEASE MAKE SURE THE AREA YOU USED IN WATER |
| | QUALITY CALS DO MATCH WITH THE AREA YOU SHOW ON |
| | DRAWINGS. |
| | 6. WATER & SEWER PLANS MUST BE APPROVED FROM 45TH |
| | STREET (MANNY G.), UTILITY DEPT BEFORE WE APPROVE AT |
| | CONSTRUCTION SERVICES. |
| | |
| | PLEASE RESPOND EACH ITEM IN DETAIL TO EXPEDITE YOUR |
| | PERMITTING PROCESS |
| | |
| | RASIK CHOKSHI805-6723 |