| Date |
Text |
| 2007-08-02 12:59:17 | ***** FAILED ***** |
| | |
| | MOST OF THE FOLLOWING COMMENTS ARE ALSO GIVEN IN YOUR |
| | PERMIT # 07030559. HOWEVER, THIS PERMIT (07051156) IS |
| | FOR STORM WATER DRAINAGE/RETENTION POND.SO PLEASE |
| | PROVIDE THE FOLLOWING INFO: |
| | |
| | 1. PLEASE PROVIDE A COPY OF NOTICE OF INTENT (NOI). |
| | PLEASE APPLY AT FDEP, NPDES STORMWATER SECTION FOR |
| | NOI. |
| | YOU CAN GET NOI INFO FROM |
| | WWW.DEP.STATE.FL.US/WATER/STORMWATER/NPDES/ |
| | NOTICE OF INTENT DEP FORM 62-621.300(4)(B), |
| | EFFECTIVE MAY 1, 2003 |
| | THIS IS KIND OF A NEW REQUIREMENTS. YOU MAY HAVE |
| | ALREADY APPLIED FOR NOI. JUST SEND US A COPY NOITHAT |
| | YOU APPLY AT FDEP, NPDES STORM WATER SECTION,. |
| | 2. PLEASE SHOW STANDARDS NOTES OF CITY OF WPB ON |
| | DRAWINGSFOR SIDEWALK WIDTH , ITS SLOPE, DRIVEWAY, |
| | PARKING, HANDICAP PARKING, PAINTPER CITY STANDARDS |
| | ETC.,, MUST MEET PER ADA,,ETC.,YOU CAN GET STANDARD |
| | NOTES OF CITY OF WPB IN A C.D. FROM 1000 45TH STREET. |
| | WE SHOULD HAVE THOSE NOTES ON YOUR DRAWINGS. FOR YOUR |
| | INFO, MANNY GONZALEZ DOES NOT DO ENG REVIEW, AT |
| | CONSTRUCTION SERVICES AS MR. CAMERO WROTE IN HIS LETTER |
| | OF 5/23/07 FOR PER PERMIT # 07030559. |
| | 3.PLEASE SHOW IN DOCUMENT, HOW DID YOU DETERMINE THE |
| | FIRST FLOOR ELEVATION? PLEASE SHOW IN CALS THAT YOU |
| | CONSIDERED,CENTER LINE OF ROAD , SIDEWALK ELEVATION, |
| | FL BLDG CODE, & FLOOD ZONE AREA OF THIS LOCATION, |
| | PLEASE SHOW ALL THESE IN YOUR DOCUMENT. PLEASEALSO |
| | SHOW IN YOUR CALCULATION THAT YOUR FLOOR ELEVATION IS |
| | HIGHENOUGH TO MEET5, 10, 25, 100 YEAR FLOOD |
| | CALCULATION. |
| | 4. PLEASE PROVIDE A COPY OF SFWMD PERMIT,, |
| | 5. WE COULD NOT FIND A COPY OF WATER QUALITY |
| | CALCULATION IN THE PACKAGE. IN PREVIOUS REV (LAST TIME) |
| | WE WROTE THAT PLEASE EXPLAIN IN YOURSTORM WATER |
| | CALCULATIONS, PAGE 2,IN CALCULATING LENGTH OF |
| | EXFILTRATION TRNECH, V= 4.736- 2.02,WHY ARE YOU |
| | DEDUCTING 2.02?, ALSO EXPLAIN ALL OTHER PARAMETERS, |
| | PLEASE GO THRU ONE MORE TIME, WE USE SFWMD CRITERIA. |
| | DETAIL OF CONTROL STRUCTURE. DO YOU KEEP ALL STORM |
| | WATER ON SITE??, OR ANY CANAL? PLEASE EXPLAIN. PLEASE |
| | ALSO RESUBMIT GEO-TECH REPORT WITH WATER QUALITY CALS. |
| | 6. PLEASE SHOW ON THE DRAWING THE SITE AREA, YOU ARE |
| | DEVELOPING FOR THIS PROJECT ONLY ?ALSO, WHAT IS TOTAL |
| | PERVIOUS,& IMPERVIOUS AREA FOR THIS PROJECT., DO YOU |
| | HAVE LAKE? PLEASE MAKE SURE THE AREA YOU USED IN WATER |
| | QUALITY CALS DO MATCH WITH THE AREA YOU SHOW ON |
| | DRAWINGS. |
| | 7. WATER & SEWER PLANS MUST BE APPROVED FROM 45TH |
| | STREET (MANNY G.), UTILITY DEPT BEFORE WE APPROVE AT |
| | CONSTRUCTION SERVICES. |
| | |
| | PLEASE RESPOND EACH ITEM IN DETAIL TO EXPEDITE YOUR |
| | PERMITTING PROCESS |
| | |
| | RASIK CHOKSHI805-6723 |