2007-07-06 14:43:40***FAILED**** PLEASE PROVIDE THE FOLLOWING:
  
 1. PLEASE PROVIDE A COPY OF NOTICE OF INTENT (NOI).
 PLEASE APPLY AT FDEP, NPDES STORMWATER SECTION FOR
 NOI.
 YOU CAN GET NOI INFO FROM
 WWW.DEP.STATE.FL.US/WATER/STORMWATER/NPDES/
 NOTICE OF INTENT DEP FORM 62-621.300(4)(B),
 EFFECTIVE MAY 1, 2003
 2. PLEASE SHOW ON DRAWINGSDUMPSTER & ITS ENCLOSURE
 DETAILS PER CITY OF WPB, &LOCATION ON DWG, LOCATION
 MUST BE ACCESSIBLE FOR PICKUP TRUCK.
 3. FIRST FLOOR ELEVATION, CENTER LINE OF ROAD ,
 SIDEWALK ELEVATION MUST MEET FLOOD ZONE AREA, & 5,10,
 25, 100 YEAR FLOOD CRITERIATO DETERMINE THE FIRST
 FLOOR ELEVATION, MUST MEET THESE MINIMUM REQUIREMENTS.
 PLEASE SHOW IN YOUR STORM WATER CALS.
 4. PLEASE SHOW ON DRAWINGTHE SITE AREA, YOU ARE
 DEVELOPING FOR THIS PROJECT . PLEASE ALSO SHOW TOTAL
 PERVIOUS,& IMPERVIOUS AREA FOR THIS PROJECT,
 LAKE,SIDEWALK, PARKING,BUILDING AREA ETC. MAKE SURE
 THESE AREAS SHOWN ON DRAWINGS MUST MATCH WITH AND USED
 IN STORM WATER QUALITY CALCULATIONS.
 5. HOW DO YOU CONNECT TO THE STORM WATER PIPES IN YOUR
 SITE? ITS DETAILS.PLEASE SHOW ALL STORM WATER PIPES
 AROUND YOUR SITE SO, WE CANSEE THE LAYOUT OF STORM
 WATER PIPES FROM ALL OTHER STORM WATER PIPES. PLEASE
 SHOW DETAIL OF THE CONTROL STRUCTURESWITH
 ELEVATIONS, NOTCHES, BLEEDING ELEVATION, ETC ON
 DRAWINGS, DO YOU HAVE EXFILTRATION TRENCHES. PLEASE
 SHOW DRY DETENTION/WET DETENTION AREAS WITH 100% FILL
 OF STORM WATER ELEVATION?
 6. ALSO PLEASE SHOW ALL CATCH BASINS NEAREST,AROUND
 YOUR SITE FOR STORM WATER DRAIN.
 7. PLEASE PROVIDE A COPY OF SFWMD PERMIT,,
 8.IN YOUR STORM WATER QUALITY CALCULATIONS,IN4.
 TREATMENT VOLUME PAGE, NO OF ACRES USED ARE CONFUSING,
 FOR EXAMPLE 14.67 ACRE, HOW DID YOU CALCULATE, I HAVE A
 PROBLEMS IN ALL NO OF ACRES USED IN STORM WATER QUALITY
 CALS IN THAT PAGE. YOU DID NOT SAY HOW DID YOU FIND NO
 OF ACRES OR GAVE US FINAL # AC-FT WHICH IS NOT
 ACCEPTABLE.
 9. PLEASE SHOW ON DRAWINGS THE POLLUTION PREVENTION
 DETAILS,CLOTHES USED FOR SILT ETC., PLANS SHOWING SILT
 FENCE AROUND THE SITE & CATCH BASINS.HEIGHT OF FENCE
 SHOULD BE HIGH ENOUGH PER FDEP TO STOP DUST &
 PARTICLES.
 10. WATER & SEWER PLANS MUST BE APPROVED FROM 45TH
 STREET (MANNY G.), UTILITY DEPT BEFORE WE APPROVED
  
 PLEASE RESPOND EACH ITEM IN DETAIL TO EXPEDITE YOUR
 PERMITTING PROCESS
  
 RASIK CHOKSHI805-6723
  
  