| Date |
Text |
| 2007-05-24 10:53:47 | |
| | YOU WROTE A NOTE ON SHEET C1.0 (4/16/07) THAT FOR ALL |
| | SIGNAGE & ALL SITE WORK SEE SEPARATE PERMITS. I COULD |
| | NOT FIND THOSE SEPARATE PERMITS. THEREFORE,PLEASE |
| | PROVIDE THE FOLLOWING INFO: |
| | |
| | 1. PLEASE SHOW STANDARDS NOTES OF CITY OF WPB ON |
| | DRAWINGSFOR SIDEWALK WIDTH , ITS SLOPE, DRIVEWAY, |
| | PARKING, HANDICAP PARKING, PAINTING DETAILS FOR PARKING |
| | PER CITY CODES ETC.,, MUST MEET PER ADA,,ETC.,YOU CAN |
| | GET STANDARD NOTES OF CITY OFWPB IN A C.D. FROM 1000 |
| | 45TH STREET. ENG DEPT.WE SHOULD HAVE THOSE NOTES ON |
| | YOUR DRAWINGS. |
| | 2. PLEASE SHOW ON DRAWINGSDUMPSTER & ITS ENCLOSURE |
| | DETAILS PER CITY OF WPB, &LOCATION ON DWG, LOCATION |
| | MUST BE ACCESSIBLE FOR PICKUP TRUCK. |
| | 3. FIRST FLOOR ELEVATION, CENTER LINE OF ROAD , |
| | SIDEWALK ELEVATION MUST MEET FLOOD ZONE AREA, & 5,10, |
| | 25, 100 YEAR FLOOD CRITERIATO DETERMINE THE FIRST |
| | FLOOR ELEVATION, MUST MEET THESE MINIMUM REQUIREMENTS. |
| | |
| | 4. PLEASE PROVIDE A COPY OF SFWMD PERMIT,, GEO-TECH |
| | REPORT AND SHOW CALCULATION FOR LENGTH OF EXFILTRATION |
| | TRENCH, & SAFETY FACTOR YOU USED IN CALCULATION OF |
| | EXFILTRATION LENGTH. |
| | 5.PLEASE SHOW STORM WATER QUALITY CALCULATIONS, WHAT |
| | CRITERIA YOU ASSUMEDFOR RUNOFF CAL.,, LIKE 1" OVER |
| | ENTIRE SITE OR2.5"CRITERIA, ETC? |
| | 6. WHAT IS THE SITE AREA, YOU ARE DEVELOPING FOR THIS |
| | PROJECT ONLY ?ALSO, WHAT IS TOTAL PERVIOUS,& IMPERVIOUS |
| | AREA FOR THIS PROJECT. |
| | 7. HOW YOU CONNECT TO THE STORM WATER PIPES IN YOUR |
| | SITE? ITS DETAILS.PLEASE SHOW ALL STORM WATER PIPES |
| | AROUND YOUR SITE SO, WE CANSEE THE BEST PIPE TO |
| | CONNECT WITH THE STORM WATERFROM ALL OTHER STORM |
| | WATER PIPES. PLEASE SHOW DETAIL OF THE CONTROL |
| | STRUCTURES WITH ELEVATIONS, NOTCHES, BLEEDING |
| | ELEVATION, ETC DID YOU USE EXFILTRATION TRENCH ? |
| | 8. POLLUTION PREVENTION DETAILS,CLOTHES USED FOR SILT |
| | ETC., PLANS SHOWING SILT FENCE AROUND THE SITE & CATCH |
| | BASINS.HEIGHT OF FENCE SHOULD BE HIGH ENOUGH PER FDEP |
| | TO STOP DUST & PARTICLES. |
| | 9. WATER & SEWER PLANS MUST BE APPROVED FROM 45TH |
| | STREET (MANNY G.), UTILITY DEPT BEFORE WE APPROVED 10. |
| | ALSO PLEASE SHOW ALL CATCH BASINS NEAREST,AROUND YOUR |
| | SITE FOR STORM WATER DRAIN. |
| | |
| | PLEASE RESPOND EACH ITEM IN DETAIL TO EXPEDITE YOUR |
| | PERMITTING PROCESS |
| | |
| | RASIK CHOKSHI805-6723 |