| 2007-05-02 10:46:28 | |
| | |
| | NONCOMPLIANT |
| | |
| | PLEASE MAKE THE FOLLOWING CORRECTIONS FOR CODE |
| | COMPLIANCE AND RESUBMIT FOR REVIEW. |
| | |
| | 1} THE PLAN INDICATES A METER AND MAIN DISCONNECT ON |
| | THE STRUCTURE, THE RISER ONLY INDICATES A MAIN ONLY. |
| | PLEASE CORRELATE TO SHOW ACTUAL CONDITIONS. |
| | |
| | 2} THE TANKLESS WATER HEATER APPEARS IN THE LOAD |
| | CALCULATIONS AS 8500 VA AND ON THE PANEL SCHEDULE AS |
| | 4500 VA, PLEASE CORRECT., INCLUDE CORRECT OCP AND |
| | CONDUCTOR SIZE. |
| | |
| | 3} THE BATHROOM AND "OUTSIDE" GFI CIRCUITS ARE NOT |
| | REQUIRED IN THE LOAD CALCULATIONS AS THEY ARE INCLUDED |
| | IN THE GENERAL LIGHTING CALCULATION. SEE 220.14(J), |
| | 2005 NEC. |
| | |
| | 4} THE AHU LOAD IN THE CALCULATION AND ON THE SCHEDULE |
| | ARE NOT THE SAME, THEREFORE THE OCP AND WIRE SIZES ARE |
| | INCORRECT. 310.16 PLEASE CORRELATE. |
| | |
| | 5} THE WASHER AND DRYER ON THE PLAN APPEAR TO BE A |
| | STACKED UNIT, BUT ARE ON SEPARATE CIRCUITS IN THE |
| | SCHEDULE. PLEASE CORRECT TO INTENDED CONDITIONS. |
| | |
| | 6} THE LOAD CALCULATIONS ARE DUPLICATED IN THE PANEL |
| | SCHEDULE AND IN THE LOAD CALCULATION |
| | SCHEDULE/WORKSHEET. THE PANEL SCHEDULE INDICATES |
| | CONNECTED LOAD AND THE CALC SHEET THE DEMAND LOAD. |
| | THERE IS NO NEED TOCALCULATE THE CONNECTED LOAD IN |
| | THE PANEL SCHEDULE. THE CONNECTED LOAD SHOULD BE SHOWN |
| | FOR CONDUCTOR AND OCP SIZE ONLY. PLEASE KEEP THIS IN |
| | MIND FOR FUTURE PLANS AS WELL AS THIS RESUB. THE |
| | REFERENCE TO 220.30 IS INCORRECT. SEE ARTICLE 220 IN |
| | THE 2005 NEC, ADOPTED DECEMBER 8, 2006. |
| | |
| | 7} THE BATH CIRCUIT PER 210.11(C)(3) IS REQUIRED IN THE |
| | SCHEDULE. |
| | |
| | 8} BOTH BATH RECEPTACLES (MASTER) MUST BE GFI PER 210.8 |
| | (A)(1). |
| | |
| | IF THERE ARE ANY QUESTIONS PLEASE CALL. |
| | |
| | BILL TROBAUGH |
| | ELECTRICAL PLANS EXAMINER |
| | CITY OF WEST PALM BEACH |
| | 561/805-6718 |