| 2008-02-25 15:59:54 | PLEASE PROVIDE FOLLOWING INFO: |
| | |
| | 1.FIRST FLOOR ELEVATION, CENTER LINE OF ROAD , SIDEWALK |
| | ELEVATION MUST MEET FL BLDG CODE, PLEASE SHOW ON THE |
| | DRAWINGS. |
| | 2. PLEASE PROVIDE A COPY OF SFWMD PERMIT,GEO TECH |
| | REPORT. |
| | 3.PLEASE SHOW STORM WATER CALCULATIONS, WHAT CRITERIA |
| | YOU ASSUMEDFOR RUNOFF CAL.,, LIKE 1" OVER ENTIRE SITE |
| | OR2.5"CRITERIA, ?PERVIOUS AREA, LIKE GREEN, |
| | LAKES, ETC,IMPERVIOUS AREA CAL., |
| | 4. WHAT IS THE SITE AREA, YOU ARE DEVELOPING FOR THIS |
| | PROJECT ONLY ? SO, WE CAN CHECK PERVIOUS, IMPERVIOUS |
| | CAL. |
| | 5. HOW DO YOU CONNECT TO THE STORM WATER PIPES IN YOUR |
| | SITE? ITS DETAILS.PLEASE SHOW ALL STORM WATER PIPES |
| | AROUND YOUR SITE SO, WE CANSEE THE BEST PIPE TO |
| | CONNECT WITH THE STORM WATERFROM ALL OTHER STORM |
| | WATER PIPES. PLEASE SHOW DETAIL OF THE CONTROL |
| | STRUCTURES WITH ELEVATIONS, NOTCHES, BLEEDING |
| | ELEVATION, ETC DID YOU USE EXFILTRATION TRENCH ? |
| | 6. POLLUTION PREVENTION DETAILS,CLOTHES USED FOR SILT |
| | ETC., PLANS SHOWING SILT FENCE AROUND THE SITE |
| | 7. WATER & SEWER PLANS MUST BE APPROVED FROM 45TH |
| | STREET (MANNY G.), UTILITY DEPT BEFORE WE APPROVED |
| | 8. ALSO PLEASE SHOW ALL CATCH BASINS NEAREST,AROUND |
| | YOUR SITE FOR STORM WATER DRAIN. |
| | |
| | PLEASE RESPOND EACH ITEM IN DETAIL IN A LETTER & ON |
| | DRAWING REVISIONS,TO EXPEDITE YOUR PERMITTING |
| | PROCESS |
| | |
| | RASIK CHOKSHI805-6723 |