| 2007-02-15 13:36:11 | PLEASE PROVIDE FOLLOWING INFO: |
| | |
| | 1. PLEASE SHOW ON DRAWINGS, STANDARDS NOTES OF CITY OF |
| | WPB FOR SIDEWALK WIDTH , ITS SLOPE, DRIVEWAY, APPROACH, |
| | PARKING, HANDICAP PARKING, PAINTPER CITY CODES |
| | ETC.,,MUST MEET ADA ETC.,ALL STANDARD NOTES OF CITY OF |
| | WPB CAN BE OBTAINED FROM 1000 45TH STREET, ENG DEPT. |
| | 2. PLEASE SHOW ON DRAWINGSDUMPSTER & ITS ENCLOSURE |
| | DETAILS PER CITY OF WPB, &LOCATION ON DWG, LOCATION |
| | MUST BE ACCESSIBLE FOR PICKUP TRUCK. |
| | 3. FIRST FLOOR ELEVATION, CENTER LINE OF ROAD , |
| | SIDEWALK ELEVATION MUST MEET FL BLDG CODE, PLEASE SHOW |
| | ON THE DRAWINGS. |
| | 4. PLEASE PROVIDE A COPY OF SFWMD PERMIT, & GEOTECH |
| | REPORT |
| | 5.PLEASE SHOW STORM WATER CALCULATIONS, WHAT CRITERIA |
| | YOU ASSUMEDFOR RUNOFF CAL.,, LIKE 1" OVER ENTIRE SITE |
| | OR2.5"CRITERIA, ?PERVIOUS AREA, LIKE GREEN, |
| | LAKES, ETC,IMPERVIOUS AREA CAL., |
| | 6. WHAT IS THE SITE AREA, YOU ARE DEVELOPING FOR THIS |
| | PROJECT ONLY ? SO, WE CAN CHECK PERVIOUS, IMPERVIOUS |
| | CAL.PL.PROVIDE TOTAL PERVIOUS/IMPERVIOUS AREA. |
| | 7. HOW DIDYOU CONNECT TO THE STORM WATER PIPES IN |
| | YOUR SITE? ITS DETAILS.PLEASE SHOW ALL STORM WATER |
| | PIPES AROUND YOUR SITE SO, WE CANSEE THE BEST PIPE TO |
| | CONNECT WITH THE STORM WATERFROM ALL OTHER STORM |
| | WATER PIPES. PLEASE SHOW DETAIL OF THE CONTROL |
| | STRUCTURES WITH ELEVATIONS, NOTCHES, BLEEDING |
| | ELEVATION, ETC DID YOU USE EXFILTRATION TRENCH ? |
| | 8. POLLUTION PREVENTION DETAILS,CLOTHES USED FOR SILT |
| | ETC., PLANS SHOWING SILT FENCE AROUND THE SITE, NEED |
| | MORE THAN 2.5 FT HIGH SILT FENCE |
| | 9. WATER & SEWER PLANS MUST BE APPROVED FROM 45TH |
| | STREET (MANNY G.), UTILITY DEPT BEFORE WE APPROVE |
| | 10. ALSO PLEASE SHOW ALL CATCH BASINS NEAREST,AROUND |
| | YOUR SITE FOR STORM WATER DRAIN. |
| | |
| | PLEASE RESPOND EACH ITEM IN DETAIL TO EXPEDITE YOUR |
| | PERMITTING PROCESS |
| | |
| | RASIK CHOKSHI805-6723 |