| 2007-07-11 16:45:30 | FAILED |
| | |
| | 1) THE PLANS WILL BE REQUIRED TO CONFORM TO THE CITY |
| | COMMISSION?S STREET CLOSURE RELOCATION PLAN.THE |
| | STREET CLOSURES AT 28TH AND 29TH STREET SHALL BE |
| | RELOCATED TO THE MID-BLOCK LOCATION (EAST OF THE |
| | PROJECT ENTRANCE).RELOCATED STREET CLOSURE LOCATIONS |
| | SHALL BE SHOWN ON THE PLANS.NOTE THAT PLANS FOR THE |
| | RELOCATED STREET CLOSURE DESIGN WILL NEED TO BE |
| | APPROVED BY THE CITY COMMISSION (JULY 16) AND |
| | CONSTRUCTED BY THE DEVELOPER.PLEASE SUBMIT THE CITY |
| | RIGHT-OF-WAY PERMIT APPROVING THE CONSTRUCTION OF THE |
| | RELOCATED STREET CLOSURES. (PARTIAL REPEAT) |
| | |
| | 2) PROVIDE THE RECORDED PUBLIC ACCESS EASEMENT FOR THAT |
| | PORTION OF THE SIDEWALK LOCATED ON THE SITE ALONG |
| | BROADWAY AVENUE AND FOR THE SIDEWALK ALONG THE ALLEY. |
| | THE EASEMENT LANGUAGE SHALL BE APPROVED BY THE OFFICE |
| | OF THE CITY ATTORNEY PRIOR TO RECORDATION. (REPEAT) |
| | |
| | 3) PROVIDE THE RECORDED PERPETUAL MAINTENANCE AGREEMENT |
| | FOR THE REBUILT, PAVERED ALLEY.THE MAINTENANCE |
| | AGREEMENT LANGUAGE SHALL BE APPROVED BY THE OFFICE OF |
| | THE CITY ATTORNEY PRIOR TO RECORDATION. (REPEAT) |
| | |
| | 4) BMUD REQUIRES THAT SIDEWALKS ALONG BROADWAY BE A |
| | MINIMUM OF 8 FEET IN CLEAR WIDTH.THE SITE PLAN |
| | (SIGNED AND SEALED 6/26/07) AND THE CIVIL PLANS |
| | (REVISION 6/25/07, SIGNED AND SEALED 6/27/07) APPROVED |
| | WITH THE FOUNDATION PERMIT SHOW THIS STANDARD BEING |
| | MET, BUT THE PLANS SUBMITTED WITH THIS PERMIT DO NOT |
| | ADDRESS THE COMMENT. |
| | |
| | 5) AN APPROVED FDOT ACCESS CONNECTION PERMIT TO MOVE |
| | THE 29TH STREET CLOSURE IS REQUIRED. (REPEAT) |
| | |
| | 6) THE APPROVED ELEVATIONS DESIGNATE THIS AS A |
| | MEDITERRANEAN STYLE BUILDING WITH A BARREL TILE ROOF. |
| | SOME PAGES/DETAILS HAVE BEEN CORRECTED (EX. SHEET |
| | A7.1), BUT THERE ARE STILL REFERENCES TO ASPHALT |
| | SHINGLES (SHEETS A5.1 AND A5.2) AND THE ENTRY OVERHANG |
| | DETAILS (SHEET A5.3) SHOW SHINGLES NOT TILE.(PARTIAL |
| | REPEAT) |
| | |
| | 7) BONDS WILL BE REQUIRED FOR ALL IMPROVEMENTS IN THE |
| | RIGHTS-OF-WAY. (REPEAT) |
| | |
| | 8) THE CONSTRUCTION STAGING PLAN APPEARS WELL THOUGHT |
| | OUT.PLEASE PROVIDE DETAILS OF THE TEMPORARY BARRIERS. |
| | THESE SHALL NOT ALLOW ANY TRAFFIC TO FLOW THROUGH TO |
| | THE NEIGHBORHOOD WHILE THE NEW CLOSURES ARE BEING |
| | RECONSTRUCTED.ADDITIONALLY, PLEASE SUBMIT FOR |
| | REQUIRED PERMITS TO PREPARE THE CONSTRUCTION STAGING |
| | AREAS. |
| | |
| | 9) PLEASE NOTE THAT THE LANDSCAPE REQUIRED IN THE |
| | STREET CLOSURES IS TO BE SABAL PALMS PER THE COMMISSION |
| | APPROVED STREET CLOSURE PLAN. |
| | |
| | 10) PLEASE REVISE SHEETS LP-1 AND LP-2 TO INCORPORATE |
| | THE REDLINE NOTES MADE BY ALAN BARATTA, LANDSCAPE |
| | PLANNER (561) 822-1462, ON ONE OF THE PERMIT SUBMITTAL |
| | SETS.CONTACT HIM DIRECTLY FOR ANY CLARIFICATION. |
| | |
| | CONTACT ERIC SCHNEIDER (561) 822-1435. |