| Plan Review Notes For Permit 06110181 |
| Permit Number |
06110181 |
|
| Review Stop |
B |
| Sequence Number |
1 |
|
| Notes |
| Date |
Text |
| 2007-01-11 18:23:17 | DENIED BY BUILDING | | | | | | 1) THE ENGINEERING FOR THE METAL FENCE IS REQUIRED TO | | | BE SIGNED,SEALED AND DATED BY THE ENGINEER PER FS | | | 471. | | | | | | 2) TWO DIFFERENT ENGINEERED DRAWINGS WERE SUBMITTED. | | | | | | 3) THE NOC WILL NEED TO BE RE-RECORDED. FS 713.13 | | | REQUIRES THE WORK TO COMMENCE WITHIN 90 DAYS AFTER THE | | | RECORDING DATE. | | | | | | ROBERT MCDOUGAL | | | BLDG. PLAN REVIEW | | | (561)805-6714 | | | |
|