| 2009-07-27 13:19:57 | FAILED |
| | DEAN LAUDERMILK, PROJECT COORDINATOR |
| | CSD: (561) 805-6716 |
| | ESD: (561) 494-1083 |
| | EMAIL: [email protected] |
| | TOO MANY CONTRADICTIONS TO APPROVE THE PLANS AS |
| | SUBMITTED. |
| | 1. GREASE TRAP ON CIVIL PLAN (2 OF 3) DOES NOT MATCH |
| | PLUMBING PLAN (P-1 & P-2). NEITHER DESIGN MATCHES OUR |
| | STANDARD DETAIL, WHICH WAS NOT INCLUDED IN THE CIVIL OR |
| | PLUMBING PLANS. |
| | 2. WATER SERVICE, METER AND BACKFLOW PREVENTER ARE TO |
| | REMAIN, PER CIVIL PLAN (2 OF 3), WHILE PLUMBING PLAN |
| | (P-2) SHOWS A NEW 1" SERVICE TO THE CITY MAIN. |
| | 3. WATER SERVICE FROM BUILDING TO THE METER AND |
| | BACKFLOW PREVENTER ARE TO REMAIN, PER CIVIL PLAN (2 OF |
| | 3), WHILE PLUMBING PLAN (P-2) SHOWS A NEW 1" SERVICE |
| | FROM THE BUILDING TO THE METER/BACKFLOW PREVENTER. |
| | 4. IRRIGATION PLAN (IR-1) SHOWS METER AND BACKFLOW |
| | PREVENTER AT NW CORNER OF SITE, THERE IS NO WATER MAIN |
| | IN THE ALLEY, THE WATER METER NEEDS TO BE ON LAKE |
| | AVENUE. IS THE INTENTION TO INSTALL A SEPARATE 1" |
| | SERVICE FOR THE IRRIGATION SYSTEM? THE PLUMBING PLAN |
| | SHOWS NO TEE IN THE LINES AND NO BACKFLOW PREVENTER FOR |
| | THE IRRIGATION SYSTEM. ALL BACKFLOW PREVENTERS NEED TO |
| | BE INSTALLED BY A LICENSED PLUMBER, NOT AN IRRIGATION |
| | COMPANY. |
| | 5. IRRIGATION PLAN (IR-1) SHOWS 5 ZONES, TWO OF THE |
| | ZONES ARE DESIGNED FOR MORE WATER THAN THE 1" WATER |
| | METER IS DESIGNED TO GIVE. THE MAXIMUM SAFE OPERATING |
| | RATE FOR A 1" METER IS 25 GPM. REDESIGN THE IRRIGATION |
| | SYSTEM ZONES SO THE MAXIMUM GPM RATE DOES NOT EXCEED 25 |
| | GPM |
| | 6. THE IRRIGATION SYSTEM WILL NEED A SEPARATE BACKFLOW |
| | PREVENTER WHICH IS CALLED OUT ON THE IRRIGATION PLAN |
| | BUT IS NOT SHOWN ON THE PLUMBING PLAN OR CIVIL PLAN. |
| | THE CIVIL PLAN (2 OF 3) SHOWS GATES ON THE EQUIPMENT |
| | ENCLOSURE OPENING TO THE EAST. THE APPROVED SITE PLAN |
| | AND THE BUILDING PLANS SHOWS THE GATE OPENING TO THE |
| | SOUTH (THE CORRECT WAY). |
| | 7. THIS PLAN HAS NOT BE REVIEWED/APPROVED BY THE |
| | ENGINEERING DEPARTMENT. WHEN THE CORRECTIONS ARE MADE |
| | SUBMIT THE CIVIL PLAN AND THE STORMWATER CALCULATIONS |
| | TO THE ENGINEERING SERVICES, ATTENTION EMERY FABIAN, |
| | THE PROJECT COORDINATOR FOR THE PROJECT. THIS NEEDS TO |
| | BE DONE PRIOR TO TURNING IN THE PLANS FOR ANOTHER |
| | CONSTRUCTION SERVICES REVIEW. THE ESD STAMP (APPROVED) |
| | NEEDS TO BE ON THE PLAN. |
| | |