Plan Review Notes
Plan Review Notes For Permit 06101156
Permit Number 06101156
Review Stop ENG
Sequence Number 5
Notes
Date Text
2009-07-27 13:19:57FAILED
 DEAN LAUDERMILK, PROJECT COORDINATOR
 CSD: (561) 805-6716
 ESD: (561) 494-1083
 EMAIL: [email protected]
 TOO MANY CONTRADICTIONS TO APPROVE THE PLANS AS
 SUBMITTED.
 1. GREASE TRAP ON CIVIL PLAN (2 OF 3) DOES NOT MATCH
 PLUMBING PLAN (P-1 & P-2). NEITHER DESIGN MATCHES OUR
 STANDARD DETAIL, WHICH WAS NOT INCLUDED IN THE CIVIL OR
 PLUMBING PLANS.
 2. WATER SERVICE, METER AND BACKFLOW PREVENTER ARE TO
 REMAIN, PER CIVIL PLAN (2 OF 3), WHILE PLUMBING PLAN
 (P-2) SHOWS A NEW 1" SERVICE TO THE CITY MAIN.
 3. WATER SERVICE FROM BUILDING TO THE METER AND
 BACKFLOW PREVENTER ARE TO REMAIN, PER CIVIL PLAN (2 OF
 3), WHILE PLUMBING PLAN (P-2) SHOWS A NEW 1" SERVICE
 FROM THE BUILDING TO THE METER/BACKFLOW PREVENTER.
 4. IRRIGATION PLAN (IR-1) SHOWS METER AND BACKFLOW
 PREVENTER AT NW CORNER OF SITE, THERE IS NO WATER MAIN
 IN THE ALLEY, THE WATER METER NEEDS TO BE ON LAKE
 AVENUE. IS THE INTENTION TO INSTALL A SEPARATE 1"
 SERVICE FOR THE IRRIGATION SYSTEM? THE PLUMBING PLAN
 SHOWS NO TEE IN THE LINES AND NO BACKFLOW PREVENTER FOR
 THE IRRIGATION SYSTEM. ALL BACKFLOW PREVENTERS NEED TO
 BE INSTALLED BY A LICENSED PLUMBER, NOT AN IRRIGATION
 COMPANY.
 5. IRRIGATION PLAN (IR-1) SHOWS 5 ZONES, TWO OF THE
 ZONES ARE DESIGNED FOR MORE WATER THAN THE 1" WATER
 METER IS DESIGNED TO GIVE. THE MAXIMUM SAFE OPERATING
 RATE FOR A 1" METER IS 25 GPM. REDESIGN THE IRRIGATION
 SYSTEM ZONES SO THE MAXIMUM GPM RATE DOES NOT EXCEED 25
 GPM
 6. THE IRRIGATION SYSTEM WILL NEED A SEPARATE BACKFLOW
 PREVENTER WHICH IS CALLED OUT ON THE IRRIGATION PLAN
 BUT IS NOT SHOWN ON THE PLUMBING PLAN OR CIVIL PLAN.
 THE CIVIL PLAN (2 OF 3) SHOWS GATES ON THE EQUIPMENT
 ENCLOSURE OPENING TO THE EAST. THE APPROVED SITE PLAN
 AND THE BUILDING PLANS SHOWS THE GATE OPENING TO THE
 SOUTH (THE CORRECT WAY).
 7. THIS PLAN HAS NOT BE REVIEWED/APPROVED BY THE
 ENGINEERING DEPARTMENT. WHEN THE CORRECTIONS ARE MADE
 SUBMIT THE CIVIL PLAN AND THE STORMWATER CALCULATIONS
 TO THE ENGINEERING SERVICES, ATTENTION EMERY FABIAN,
 THE PROJECT COORDINATOR FOR THE PROJECT. THIS NEEDS TO
 BE DONE PRIOR TO TURNING IN THE PLANS FOR ANOTHER
 CONSTRUCTION SERVICES REVIEW. THE ESD STAMP (APPROVED)
 NEEDS TO BE ON THE PLAN.
  