| Date |
Text |
| 2006-12-16 17:53:18 | DENIED |
| | REFERENCE: FBC-2004 FUEL GAS |
| | |
| | 1. SEPARATE GAS PERMIT REQUIRED. THE FOLLOWING |
| | INFORMATION IS REQUIRED FOR THE GAS PERMIT: |
| | |
| | A. SUBMIT AN ISOMETRIC DRAWING THAT |
| | CLEARLY SHOWS ALL CUT SECTIONS OF PIPE |
| | AND CORRESPONDING LENGTHS PER FBC-2004 |
| | FUEL GAS CODE. - RISER DOES NOT REFLECT |
| | THE FLOOR PLAN. OFFSETS BETWEEN THE |
| | METER AND THE RISER ARE NOT SHOWN. - |
| | INDICATE WHAT THE RISERS ABOVE THE TEE |
| | AT THE TOP OF THE RISER AND AT THE |
| | GENERATOR ARE FOR. FUTURE BTU LOAD AND |
| | DISTANCE MAY REQUIRE CHANGES IN THE |
| | GAS SYSTEM WHEN ADDED. |
| | |
| | B. SHOW TYPE OF PIPING MATERIAL BEING |
| | INSTALLED, ALL PIPE SIZES, (AND THE EDH |
| | NUMBER OF CORRUGATED STAINLESS STEEL |
| | TUBING FOR EACH PIPE SIZE IF BEING USED. |
| | |
| | C. TYPE OF GAS, (LP OR NATURAL). |
| | |
| | D. BTU LOAD OF EACH APPLIANCE AND THE |
| | TOTAL BTU LOAD ON THE SYSTEM. REFER TO |
| | THE FBC-2004 FUEL GAS CODE SECS. 401.8 |
| | THRU 402.6.1 AND TABLES 402.4(1) THRU |
| | 402.4(33). |
| | |
| | E. SHOW THE DISTANCE FROM THE POINT OF |
| | DELIVERY, (METER), TO THE MOST REMOTE |
| | OUTLET IN THE BUILDING AND/OR SYSTEM PER |
| | FBC-2004 FUEL GAS CODE APPENDIX A - USE |
| | OF CAPACITY TABLES A.3.1(4). |
| | |
| | F. INDICATE THE DELIVERY PRESSURE (PSI) |
| | PER FBC-2004 FUEL GAS CODE SEC. 402.2. |
| | NATURAL GAS SPECIFY .5 PSI OR 2 PSI. |
| | |
| | G. SUBMIT MANUFACTURE SHEETS FOR ALL GAS |
| | EQUIPMENT TO VERIFY COMPLIANCE WITH |
| | STANDARDS NFPA 54, NFPA 58, AND THE |
| | FBC-2004 FUEL GAS CODE SEC 402.2. |
| | |
| | H. CLEARLY SHOW THE LOCATION AND CAP- |
| | ACITY OF LP TANK(S), TYPE OF TANK (DOT |
| | OR ASME), THE DISTANCE OF THE TANK FROM |
| | THE BUILDING AND ADJACENT PROPERTY LINES |
| | THE DISTANCE OF THE TANK FROM ALL SOUR- |
| | CES OF IGNITION, OTHER CONTAINERS, BUILD- |
| | INGS, AND THE LOCATION OF ANY BUILDING |
| | OPENINGS BELOW THE RELIEF VALVE OF THE |
| | TANK PER NFPA 58, TABLE 3-2.2.2. |
| | |
| | I. CLEARLY INDICATE ON THE PLAN IF THE |
| | LP TANK IS ABOVE OR BELOW GROUND, AND |
| | SHOW REQUIRED PROTECTION OF THE TANK AND APPURTENANCES |
| | PER NFPA 58. IF THE TANK |
| | IS BELOW GROUND THE CONTAINER SHALL BE |
| | SECURILY ANCHORED PER NFPA 58 SECTION |
| | 3-2.2.7(H). |
| | |
| | REVIEW BY KEN STEVENS |
| | (561) 805-6721 |
| | FAX (561) 805-6731 |
| | E-MAIL [email protected] |