| 2007-01-26 11:01:28 | PLEASE EXPLAIN IN A LETTER EACH OF THE ITEMS BELOW AND |
| | IN DRAWING REVISION BLOCK,WHAT CHANGES YOU MADE AFTER |
| | 11/13/06 OUR APPROVAL. |
| | |
| | 1. ANY CHANGES IN STANDARDS NOTES OF CITY OF WPB ON |
| | DRAWINGSFOR SIDEWALK WIDTH , ITS SLOPE, DRIVEWAY, |
| | PARKING, HANDICAP PARKING, PAINT ? |
| | 2.ANY CHANGES IN DUMPSTER & ITS ENCLOSURE DETAILS ? |
| | LOCATION ON DWG, LOCATION MUST BE ACCESSIBLE FOR PICKUP |
| | TRUCK?. |
| | 3. ANY CHANGES INFIRST FLOOR ELEVATION, CENTER LINE |
| | OF ROAD , SIDEWALK ELEVATION?MUST MEET FL BLDG CODE, |
| | PLEASE SHOW ON THE DRAWINGS. |
| | 4. ANY CHANGES INSFWMD PERMIT? ANY CHANGES IN GEO |
| | TECH REPORT? |
| | 5. ANY CHAGES IN STORM WATER CALCULATIONS, ? ANY |
| | CHANGES IN PERVIOUS AREA, LIKE GREEN, LAKES, ETC, |
| | IMPERVIOUS AREA CAL.?, |
| | 6.ANY CHANGES IN THE SITE AREA, YOU ARE DEVELOPING FOR |
| | THIS PROJECT ? SO, WE CAN CHECK PERVIOUS, IMPERVIOUS |
| | CAL. |
| | 7. ANY CHAGES IN CONNECTTING THE STORM WATER PIPES IN |
| | YOUR SITE? ITS DETAILS. |
| | 8. ANY CHANGES IN STORM WATER PIPES AROUND YOUR SITE? |
| | SO, WE CANSEE THE BEST PIPE TO CONNECT WITH THE STORM |
| | WATERFROM ALL OTHER STORM WATER PIPES. PLEASE SHOW |
| | DETAIL OF THE CONTROL STRUCTURES WITH ELEVATIONS, |
| | NOTCHES, BLEEDING ELEVATION, ETC DID YOU CHANGE |
| | EXFILTRATION TRENCH ? |
| | 9.ANY CHAGES INPOLLUTION PREVENTION DETAILS,CLOTHES |
| | USED FOR SILT ETC.?,PLAN MUSTPLANS SHOWSILT FENCE |
| | AROUND THE SITE |
| | 10.ANY CHANGES INWATER & SEWER PLANS? MUST BE |
| | APPROVED FROM 45TH STREET (MANNY G.), UTILITY DEPT |
| | BEFORE WE APPROVED |
| | 11.ANY CHANGES IN CATCH BASINS NEAREST YOUR SITE, AND |
| | AROUND YOUR SITE FOR STORM WATER DRAIN? |
| | |
| | RASIK CHOKSHI805-6723 |