2006-10-16 08:42:34 
 DENIED
  
 1) A RECORDED COPY OF THE NOTICE OF COMMENCEMENT
 MUST BE SUBMITTED BEFORE A
 PERMIT CAN BE ISSUED.
  
 2) IMPACT FEES MUST BE PAID TO PALM
 BEACH COUNTY, PLANS STAMPED BY THEM AND
 COPY OF RECEIPT SUBMITTED TO CITY OF
 WEST PALM BEACH BUILDING DEPARTMENT,
 BEFORE A BUILDING PERMIT CAN BE ISSUED.
  
 3) THE VALUE FOR THE SCOPE OF WORK HAS BEEN INCREASED
 TO $ 83,805.00. THE FEES HAVE BEEN ADJUSTED.
  
 4) THE ENERGY CALCULATION FORMS THAT WERE SUBMITTED CAN
 ONLY BE USED FOR ADDITIONS OF 600 SQFT OR LESS. THIS
 ADDITION IS 952 SQFT.
 SUBMIT THE CORRECT FORMS. SEE FBC 13-6.
  
 5) PROVIDE A DRAINAGE PLAN FOR THE LOT AS REQUIRED BY
 FBC 401.3.
  
 6) FBC R 403.1.4 REQUIRES EXTERIOR FOOTINGS TO BE A
 MINIMUM OF 12" BELOW FINAL GRADE. PLEASE INDICATE THIS
 ON SETION F1 ON SHEET A3.0.
  
 7) WALL SECTION B ON A5.0 SPECIFIES AN 18" THICK
 FOOTING AND F1 ON A3.0 HAS A 16" THICK FOOTING. PLEASE
 CLARIFY.
  
 8) THE UPLIFT VALUE FOR THE SIMPSON LUS 210 SHOULD BE
 1165 #, NOT 3015 # PER THE 2006 SIMPSON CATALOG. PLEASE
 CORRECT THE TRUSS ANCHOR SCHEDULES ON A4.0 AND A 4.1.
  
 9) THE SIMPSON LSSU 410 REQUIRES (18) 16D NAILS TO THE
 STRUCTURE PER THE CATALOG. PLEASE CORRECT.
  
 10) THE PLYWOOD ROOF SHEATHING NOTES ON A4.1 CONTAINS
 SEVERAL ERRORS. THE NOTES SPECIFY 3 ' OK (TYPO FOR OC)
 WHICH CONFLICTS WITH THE 4"0C SPECIFIED IN THE SCHEDULE
 ON THE SAME PAGE. THE NOTES STATE THAT ZONE 1 CAN BE
 ASSUMED THROUGHOUT THE ROOF. THIS IS INCORRECT AS ZONES
 2 AND 3 REQUIRE ENHANCED FASTENING. THE NOTE ALSO
 SPECS. 1-3/4" NAILS WHICH IS ALSO INCORRECT. THE
 MINIMUM NAILS REQUIRED ARE 8D (2-1/2" ).
  
 11) THERE IS A TYPO IN THE SCHEDULES ON A4.0 AND A4.1,
 THE WORD SHOULD BE SHANK NOT SHARK. PLEASE CORRECT.
  
 12) THE LIVE LOAD FOR BALCONIES SHOULD BE 60 PSF UNDER
 STRUCTURAL NOTES ON SHEET D1.
  
 13) FBC R704 REQUIRES CLEARANCE OF NOT LESS THAN 6"
 BETWEEN EXTERIOR WALL COVERINGS AND THE FINISH GRADE
 FOR TERMITE INSPECTION. FBC R319.1(5)REQUIRES WOOD
 SIDIN, SHEATHING AND WALL FRAMING TO BE PRESSURE
 TREATED OR DECAY-RESISTANT WOOD ORHAVE CLEARANCE OF
 AT LEAST 6 " FROM THE GROUND. FBC R404.1.6 REQUIRES
 CONCRETE FOUNDATION WALLS TO EXTEND 6" ABOVE FINISHED
 GRADE. PLEASE REVISE FOOTING DETAILS AND SECTIONS TO
 COMPLY.
  
 14) SPECIFY THE REQUIRED ATTIC VENTILATION FOR THE
 SECOND FLOOR. SEE FBC R806.1.
  
 15) SHOW COMPLIANCE WITH FBC R320.7 WHICH REQUIRES ALL
 BUILDINGS WITH EAVES LESS THAN 6"TO HAVE GUTTERS AND
 DOWNSPOUTS THAT DISCHARGE 1 FOOT FROM THE STRUCTURE.
  
 16) SPECIFY THE 2 LAYERS OF UNDERLAYMENT FOR THE 3:12
 PITCH CEMENT TILE ROOF THAT IS REQUIRED BY FBC
 R905.3.3.1 FOR LOW SLOPE ROOFS.
  
 17) PROVIDE STRUCTURAL DETAILS FOR THE SECOND FLOOR
 DECK THAT ALSO SPECIFIES SPACING OF INTERMEDIATE RAILS.
 SEE FBC R312 AND R301.5.
  
 18) PROVIDE A DETAIL FOR THE REQUIRED GUARD AT THE OPEN
 SIDES OF THE STAIRS, SHOWING COMPLIANCE WITH FBC
 R312.1, R312.2.2 AND TABLE R 301.5.
  
 19) ON SHEET A3.0 THE FOOTING SECTION TAG ON THE LEFT
 SIDE OF THE FOUNDATION PLAN IS INCORRECTLY GIVEN AS
 (F2). IT SHOULD BE (F1) AT THIS LOCATION.
  
 20) PROVIDE HANDRAIL DETAILS SHOWING COMPLIANCE WITH
 FBC R311.5.6, 311.5.6.1 AND 311.5.6.3.
  
 21) CITY OF WPB AMENDMENTS TO FBC 106.3.3 REQUIRES THE
 DESIGNER OF RECORD FOR THE PROJECT TO REVIEW AND
 APPROVE IN WRITING THE PRODUCT APPROVALS.
  
 22) SPECIFYON THE PRODUCT APPROVAL NOA FOR THE MONIER
 SPANISH "S" CONCRETE TILE, WHICH ONE OF THE METHODS OF
 ATTACHMENTS LISTED WILL BE USED TO INSTALL THE THE
 TILE.
  
 23) SPECIFY WHICH ONE OF THE APPROVED ASSEMBLIES AND
 DESIGN PRESSURE LISTED IN THE NOA FOR THE GAF BUR
 SYSTEM WILL BE INSTALLED.
  
 24) THE PRODUCT APPROVAL SUBMITTED FOR THE PGT SH-4000
 WINDOWS IS NOT FOR IMPACT RESISTANT WINDOWS AS
 SPECIFIED ON THE PLANS. IT IS ALSO EXPIRED.
  
 25) THE PRODUCT APPROVAL NOA FOR THE PGT HR710 IMPACT
 WINDOW IS EXPIRED. THE CURRENT ONE IS NOA 03-0612.06
 FOR FL 242-R3.
  
 26) SUBMIT PRODUCT APPROVALS FOR THE IMPACT RESISTANT
 FIXED GLASS WINDOW.
  
 27) SUBMIT PRODUCT APPROVALS FOR THE IMPACT RESISTANT
 STRUCTURAL WINDOW MULLIONS.
  
 28) PR0VIDE A DETAIL INDICATING HOW THE DECK WILL BE
 WATERPROOFED SO THAT WHEN DECKING IS NAILED THROUGH THE
 ROOF MEMBRANE IT WILL NOT LEAK. ALSO SPECIFY THE
 FLASHING BETWEEN THE DECK AND THE EXTERIORWALL.
  
 ROBERT MCDOUGAL
 BLDG. PLAN REVIEW
 (561)805-6714


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved