| 2006-07-11 00:00:00 | ******DENIED****** |
| | REFERENCE: FBC-2004 FUEL GAS |
| | FBC-2004 CHAPTER 1 |
| | |
| | THE FOLLOWING INFORMATION IS REQUIRED |
| | FOR PLAN REVIEW FOR A GAS PERMIT: |
| | |
| | 1. TYPE OF GAS, (LP OR NATURAL) PLEASE |
| | INDICATE THIS ON THE DRAWING. |
| | 2. BTU LOAD OF EACH APPLIANCE AND THE |
| | TOTAL BTU LOAD ON THE SYSTEM. REFER TO |
| | THE FBC-2004 FUEL GAS CODE SECS. 401.8 |
| | THRU 402.6.1 AND TABLES 402.4(1) THRU |
| | 402.4(33). PLEASE INDICATE THE GENERATOR |
| | BTU LOAD ON DRAWING. |
| | 3. SUBMIT MANUFACTURE SHEETS FOR ALL GAS |
| | EQUIPMENT TO VERIFY COMPLIANCE WITH |
| | STANDARDS NFPA 54, NFPA 58, AND THE |
| | FBC-2004 FUEL GAS CODE SEC 402.2. PLEASE |
| | PROVIDE MANUFACTURE SHEETS FOR THE 1ST |
| | AND 2ND STAGE REGULATORS AND INDICATE |
| | THEIR LOCATION ON THE ISOMETRIC DRAWING. |
| | 4. CLEARLY INDICATE ON THE PLAN IF THE |
| | LP TANK IS ABOVE OR BELOW GROUND, AND |
| | SHOW REQUIRED PROTECTION OF THE TANK AND |
| | APPURTENANCES PER NFPA 58. IF THE TANK |
| | IS BELOW GROUND THE CONTAINER SHALL BE |
| | SECURILY ANCHORED PER NFPA 58 SECTION |
| | 3-2.2.7(H). PLEASE INDICATE ON THE |
| | SURVEY AND ISOMETRIC DRAWING THE PROPANE |
| | TANK SIZE AND IF THE TANK IS ABOVE OR |
| | BELOW GROUND. |
| | 5. FBC-2004 CHAPTER 1,SECTION 106.3.4.2: |
| | THE PERSON RESPONSIBLE FOR THE DESIGN OF |
| | THE DRAWING SHALL CLEARLY PRINT AND SIGN |
| | NAME, AND ALSO DATE DRAWING. PLEASE DO |
| | THIS PRIOR TO RESUBMITTING. |
| | |
| | **IN ORDER TO EXPIDITE PLAN REVIEW: WHEN |
| | RESUBMITTING, PLEASE REPLACE ONLY SHEETS |
| | WHICH HAVE CHANGED AND PROVIDE ONE COPY |
| | OF ALL OLD/VOIDED SHEETS FOR REFERENCE |
| | ONLY. |
| | |
| | END OF COMMENTS: |
| | |
| | REVIEW BY MIKE PERSON |
| | (561) 805-6730 |
| | FAX (561) 805-6731 |
| | E-MAIL [email protected] |
| | UNDER SUPERVISION OF K.STEVENS |
| | (561) 805-6721 |
| | |
| | |
| | |
| | |
| | |
| | |
| | |