| 2007-09-26 14:20:58 | REVISION DENIED |
| | REFERENCE: |
| | ** FBC-2004 WITH 05 & 06 REVISIONS, PLUMBING. |
| | ** FBC-2004 CHAPTER 1, THE CITY OF |
| | WEST PALM BEACH AMENDMENTS. |
| | ** FLORIDA ADMINISTRATIVE CODE (FAC). |
| | ** FLORIDA STATUTES (FS). |
| | |
| | THE FOLLOWING CORRECTIONS/INFORMATION ARE REQUIRED FOR |
| | PLUMBING PLAN REVIEW TO MEET CODE COMPLIANCE ON THE |
| | RESUBMITTED REVISION: |
| | |
| | 1. SHEET M2-1 PLUMBING RISER DIAGRAM DOES NOT REFLECT |
| | THE FLOOR PLAN PER FBC-2004 CHAPTER 1, SECTION 106.1.1 |
| | INFORMATION ON CONSTRUCTION |
| | DOCUMENTS. CONSTRUCTION DOCUMENTS SHALL |
| | BE OF SUFFICIENT CLARITY TO INDICATE THE |
| | LOCATION, NATURE AND EXTENT OF THE WORK |
| | PROPOSED AND SHOW IN DETAIL THAT IT WILL |
| | CONFORM TO THE PROVISIONS OF THIS CODE |
| | AND RELAVENT LAWS, ORDINANCES, RULES AND REGULATIONS, |
| | AS DETERMINED BY THE |
| | BUILDING OFFICIAL. PLEASE CORRECT THE FOLLOWING ON THE |
| | RESUBMITTAL. |
| | |
| | A} THE DOUBLE/BOWL KITCHEN SINK WITH DISHWASHER DOES |
| | NOT REFLECT THE FLOOR PLAN. ONE BOWL IS BEING INDICATED |
| | OUTSIDE OF THE BUILDING AND THE DISHWASHER DRAIN PER |
| | FBC-2004 W/05 & 06 REV SECTION 802.2 SHALL DISCHARGE |
| | INTO A WYE-BRANCH FITTING ON THE TAILPIECE OF THE |
| | KITCHEN SINK OR THE DISHWASHER CONNECTION OF A FOOD |
| | WASTE GRINDER. PLEASE CORRECT ON THE RESUBMITTED |
| | REVISION. |
| | |
| | B} WASHER IN LAUNDRY ROOM DOES NOT REFLECT THE FLOOR |
| | PLAN. WASHER IS BEING INDICATED OUTSIDE OF THE |
| | BUILDING. PLEASE CORRECT ON THE RESUBMITTED REVISION. |
| | |
| | 2. SHEET M2-1 PLUMBING RISER DIAGRAM THE AIR |
| | ADMITTANCE VALVES (STUDOR VENTS) ARE INDICATED WRONG |
| | PER FBC-2004 W/05 & 06 REV. PLUMBING SECTION 917.4 THE |
| | AIR ADMITTANCE VALVE SHALL BE LOCATED A MINIMUM OF 4 |
| | INCHES ABOVE THE HORIZONTAL BRANCH DRAIN OR FIXTURE |
| | DRAIN BEING VENTED. PLEASE CORRECT ON THE RESUBMITTED |
| | REVISION. |
| | |
| | 3. SHEET M2-1 PLUMBING RISER DIAGRAM: PRE FBC-2004 |
| | W/05 & 06 REV. PLUMBING SECTION708.3.5 BUILDING DRAIN |
| | AND BUILDING |
| | SEWER JUNCTION. THERE SHALL BE A |
| | TWO-WAY CLEANOUT NEAR THE JUNCTION OF THE |
| | BUILDING DRAIN AND THE BUILDING SEWER. |
| | |
| | |
| | ********IMPORTANT INFORMATION********** |
| | PLEASE REFERENCE THE RED LINE SANITARY PLUMBING RISER |
| | DIAGRAM ON SHEET M2-1 THAT REFLECTS THE FLOOR PLAN AND |
| | IS CODE COMPLIANT FOR THE REVISION RESUBMITTAL. THERE |
| | IS ONLY ONE CORRECTED DRAWING IN RED INK ON THE |
| | INDICATED PLAN SHEET BY THIS PLAN EXAMINER FOR |
| | REFERENCE FOR THE RESUBMITTAL. REVISION WILL NOT PASS |
| | PLUMBING PLAN REVIEW UNTIL ALL REQUESTED PLUMBING |
| | CORRECTIONS ARE MET. |
| | |
| | END OF COMMENTS: |
| | |
| | REVIEW BY: MIKE PERSON |
| | PLUMBING PLANS EXAMINER |
| | (561) 805-6730 |
| | FAX (561) 805-6731 |
| | E-MAIL: [email protected] |
| | |