| 2006-05-24 00:00:00 | ******DENIED****** |
| | REFERENCE:FBC-2004 PLUMBING |
| | FBC-2004 CHAPTER 1 |
| | |
| | THE FOLLOWING INFORMATION IS REQUIRED |
| | FOR PLUMBING PLAN REVIEW FOR A PERMIT: |
| | |
| | 1. THE SANITARY PLUMBING ISOMETRIC RISER |
| | DIAGRAM ON SHEET D3 DOES NOT REFLECT THE |
| | FLOOR PLAN ON SHEET F1. THE FOLLOWING |
| | ARE MINIMUM REQUIREMENTS FOR THE |
| | SANITARY PLUMBING ISOMETRIC RISER |
| | DIAGRAM. |
| | (A) 106.3.5.4 RESIDENTIAL (ONE AND TWO |
| | FAMILY) SUBMIT A PLUMBING SANITARY |
| | ISOMETRIC RISER DIAGRAM INDICATING ALL |
| | WASTE, VENTS, TRAPS WITH SIZES, AND |
| | CLEANOUT LOCATIONS.(NOTE: PIPE SIZES NOT |
| | INDICATED FOR THE TUB, LAV, W/C, AND |
| | SINK IN WET BAR IS MIS LABELED LAV AND |
| | BOTH BOWLS OF SINK NEED TO BE INDICATED |
| | AND SIZED. PLEASE REFERENCE CORRECTED |
| | DRAWING ON SHEET D3 FOR RESUBMITTAL.) |
| | 2. THE FOLLOWING ARE REQUIREMENTS FOR |
| | CLEANOUT LOCATIONS ON THE PLBG. SANITARY |
| | ISO. RISER DIAGRAM. PLEASE REFERENCE |
| | CORRECTED DRAWING ON SHEET D3 FOR |
| | RESUBMITTAL. |
| | (A) 708.3.4 BASE OF STACK. A CLEANOUT |
| | SHALL BE PROVIDED AT THE BASE OF EACH |
| | WASTE OR SOIL STACK |
| | (B) 708.3.5 BUILDING DRAIN AND BUILDING |
| | SEWER JUNCTION. THERE SHALL BE A |
| | CLEANOUT NEAR THE JUNCTION OF THE |
| | BUILDING DRAIN AND THE BUILDING SEWER. |
| | 3. THE TUB INDICATED ON SHEET D3 |
| | SANITARY PLBG. ISO. RISER DIAGRAM IS NOT |
| | VENTED PER SECTION 901.2.1. |
| | 4. SEE EXAMPLE OF PLBG. ISO. RISER |
| | DIAGRAM THAT MEETS CODE ATTACHED TO PLBG |
| | COMMENTS FOR RESUBMITTAL REFERENCE. |
| | |
| | END OF COMMENTS: |
| | |
| | REVIEW BY MIKE PERSON |
| | (561) 805-6730 |
| | FAX (561) 805-6731 |
| | E-MAIL [email protected] |
| | UNDER SUPERVISION OF K.STEVENS |
| | (561) 805-6721 |
| | |