| 2006-09-25 00:00:00 | ***** PLEASE KNOW AS OF 9/25/06 |
| | MECHANICAL REVIEW NOTES NOT COMPLETE, |
| | PLANS MAY BE PICKED , HOWEVER PLEASE BE |
| | AWARE NOTES FOR MECHANICAL MAY FOLLOW. |
| 2006-09-21 00:00:00 | DENIED: |
| | 1.PLAN SHEET H0.03 DETAIL 26 - ROOFTOP |
| | MOUNTING DETAIL FOR THE CONDENSING UNIT |
| | DOES NOT COMPLY WITH 2004 FBC 1509.7. |
| | |
| | 2.PLAN SHEET H0.03 DETAIL 30 - CURB |
| | DETAIL DOES NOT SPECIFY HEIGHT OF THE |
| | CURB.PER 2004 FBC 1509.7, RAISED CURBS |
| | SHALL BE A MINIMUM OF 8" ABOVE THE ROOF |
| | SURFACE. |
| | |
| | 3.H1.01 EXHAUST TERMINATION FROM CIF-6 |
| | IS 5' X 3' LOUVER OVER A DOOR.PER 2004 |
| | FMC 401.5.2 EXHAUST AIR SHALL BE LOCATED |
| | AS NOT TO CREATE A NUISANCE, AIR SHALL |
| | NOT BE DIRECTED ONTO WALKWAYS. |
| | |
| | 4.PLAN SHEET H1.02, CO SENSORS ARE |
| | INDICATED, PLAN DOES NOT SPECIFY AT WHAT |
| | PARTS PER MILLION (PPM).PER 2004 FMC |
| | 404.1, A MAXIMUM OF 25 PPM IS THE |
| | REQUIREMENT FOR THE ACTIVATION OF THE |
| | FANS. |
| | |
| | 5.PLAN SHEET H1.02 PF-1 & 2 GARAGE |
| | EXHAUST, PLEASE CLARIFY AIR MAKE-UP FOR |
| | EACH FLOOR.PLEASE PROVIDE |
| | CALCULATIONS.CO SENSORS SHALL BE TIED |
| | TO THE EMERGENCY POWER. |
| | |
| | 6.PLAN SHEET H1.02 PLEASE INDICATE IF |
| | THE CONDENSING UNITS ARE LOCATED INSIDE |
| | OR OUTDOORS. |
| | |
| | 7.PLAN SHEET H1.03 CIF-3 EXHAUST FAN |
| | FROM STORAGE ROOM 304 TERMINATES INTO |
| | THE GARAGE INSTEAD OF THE OUTDOORS AS |
| | REQUIRED BY 2004 FMC 501.2 |
| | |
| | 8.PLAN SHEET H1.03, H1.05PLEASE |
| | CLARIFY STORAGE (RMS 302,402,502) |
| | MAKE-UP AIR FROM THE GARAGE AREA & |
| | EXHAUST TERMINATES INTO THE GARAGE AREA |
| | ALSO. |
| | |
| | 9.PLAN SHEET H1.06 RM 614 INDICATES A |
| | 6"X6" SUPPLY DUCT PENETRATING THE 1 HR |
| | PARTITION.PLEASE NOTE, DUCT SHALL |
| | COMPLY WITH THE EXCEPTIONS IN FMC |
| | 607.5.3 OF THE 2004 CODE OR INSTALL A |
| | FIRE DAMPER.PLEASE CLARIFY. |
| | |
| | 9.PLAN SHEET H1.17 INDICATES 4 FT |
| | STEEL DUNNAGE, PLEASE PROVIDE DETAIL OF |
| | THE SUPPORT ANCHORING TO THE ROOF, |
| | CLEARANCE BETWEEN THE ROOF SURFACE AND |
| | SUPORT RAIL, AND THE ACHORING OF SPRING |
| | ISOLATORS TO THE STEEL. |
| | |
| | 11. PLAN SHEET H1.18 & DETAIL 26 ON PLAN |
| | SHEET H0.03.SUPPORTS FOR ACCU1 |
| | & ACCU2 ON SLEEPERS.PER 2004 FBC |
| | 1509.7ROOF MOUNTED EQUIPMENT WHERE |
| | ROOFING MATERIALS ARE UNDERNEATH THE |
| | EQUIPMENT A ROOF STAND IS REQUIRED IN |
| | ACCORDANCE WITH TABLE 1509.PLEASE SHOW |
| | THE ANCHORING DETAILS. |
| | |
| | 12. PLEASE PROVIDE SUBMITTALS FOR |
| | EQUIPMENT. |
| | |
| | 13. PROVIDE INFORMATION ABOUT THE |
| | EMERGENCY GENERATOR.PLEASE INDICATE |
| | FUEL TYPE & STORAGE.PROVIDE |
| | VENTILATION INFORMATION SHOULD THE |
| | GENERATOR BE LOCATED INSIDE THE |
| | BUILDING. |
| | |
| | 14. PLANS ARE TO BE SIGNED, SEALED, AND |
| | DATED BY THE ENGINEER IN ACCORDANCE WITH |
| | FS 471.025 & FAC 61G15-23.002. |
| | |