| 2007-02-06 16:19:15 | DENIED FIFTH TIME |
| | REFERENCE: FBC-2004 PLUMBING |
| | |
| | THE FOLLOWING ITEMS ARE STILL REQUIRED TO BE CORRECTED |
| | FOR PLUMBING PLAN REVIEW TO MEET CODE COMPLIANCE: |
| | |
| | 1. SHEET P-1 AND P-2 SANITARY ISOMETRICS AND PLUMBING |
| | PLAN WASHING MACHINE BRANCH DRAINS ARE STILL SIZED |
| | WRONG ON ALL UNITS ( 708 FIRST AND SECOND FLOOR, 708 |
| | 1/2A AND 708 1/2B) PER FBC-2004 PLUMBING, SECTION 406.3 |
| | THEY NEED TO BE THREE INCH (3") NOT TWO INCH (2"). |
| | PLEASE CORRECT AND RESUBMIT. |
| | |
| | 2. SEE ATTACHED NOTICE FS 553.80 (2) (B) REGAURDING |
| | FOUR TIMES THE FEE. |
| | |
| | THE FOLLWING ARE NEW ITEMS THAT NEED TO BE CORRECTED |
| | FOR PLUMBING PLAN REVIEW TO MEET CODE COMPLIANCE: |
| | |
| | 3. SHEET P-1 GENERAL NOTES #16 DELETE "APPROVED AIR |
| | CHAMBERS" AND ADD IN ITS PLACE THE FOLLOWING " WATER |
| | HAMMER ARRESTORS TO BE INSTALLED PER FBC-2004 PLUMBING, |
| | SECTION 604.9." |
| | |
| | 4. SHEET P-1 NOTE ON TUB AND SHOWER VALVES: PLEASE ADD |
| | "TUB AND SHOWER VALVES TO BE INSTALLED PER FBC-2004 |
| | PLUMBING, SECTION 424.3. |
| | |
| | 5. SHEET P-2 UNIT 708 1/2A WATER ISOMETRIC: A} PER |
| | FBC-2004 PLUMBING, SECTION 606.1 (2) FULL-OPEN VALVE |
| | REQUIRED ON THE WATER DISTRIBUTION SUPPLY PIPE AT THE |
| | ENTRANCE INTO THE BUILDING. B} HOT AND COLD WATER ARE |
| | CROSSED ON THE WASHER, KITCHEN, AND LAV, PER FBC-2004 |
| | PLUMBING SECTION 607.4 FLOW OF HOT WATER TO FIXTURES |
| | SHALL BE INSTALLED AND ADJUSTED SO THAT THE FLOW OF HOT |
| | WATER FROM THE FITTING CORRESPONDS TO THE LEFT-SIDE OF |
| | THE FIXTURE FITTING. C} WATER SERVICE NEEDS TO SUPPLY |
| | THE WATER DISTRIBUTION PIPING FIRST THEN BRANCH TO THE |
| | WATER HEATER AS THE CORRECTED DRAWING INDICATES, NOT |
| | DIRECTLY SUPPLY THE WATER HEATER AS SHOWN. PLEASE |
| | CORRECT AND RESUBMIT. D} PLEASE CLARIFY THE THIRD WATER |
| | CONNECTION TO THE WASHER. IS IT NEEDED, IF NOT PLEASE |
| | DELETE. |
| | |
| | 6. SHEET P-2 708 1/2B WATER ISOMETRIC: A} PER FBC-2004 |
| | PLUMBING, SECTION 606.1 (2) FULL-OPEN VALVE REQUIRED ON |
| | THE WATER DISTRIBUTION SUPPLY PIPE AT THE ENTRANCE INTO |
| | THE BUILDING. B} HOT AND COLD WATER ARE CROSSED ON THE |
| | LAV AND WASHER, PER FBC-2004 PLUMBING SECTION 607.4 |
| | FLOW OF HOT WATER TO FIXTURES SHALL BE INSTALLED AND |
| | ADJUSTED SO THAT THE FLOW OF HOT WATER FROM THE FITTING |
| | CORRESPONDS TO THE LEFT-SIDE OF THE FIXTURE FITTING. C} |
| | WATER SERVICE NEEDS TO SUPPLY THE WATER DISTRIBUTION |
| | PIPING FIRST THEN BRANCH TO THE WATER HEATER AS THE |
| | CORRECTED DRAWING INDICATES, NOT DIRECTLY SUPPLY THE |
| | WATER HEATER AS SHOWN. PLEASE CORRECT AND RESUBMIT. D} |
| | IS IT THE INTENT TO HAVE HOT WATER SUPPLIED TO THE HOSE |
| | BIBB AS INDICATED. IF NOT PLEASE CORRECT AND RESUBMIT. |
| | E} PLEASE CLARIFY THE THIRD WATER CONNECTION TO THE |
| | WASHER. IS IT NEEDED, IF NOT PLEASE DELETE. |
| | |
| | **********IMPORTANT INFORMATION |
| | IN ORDER TO EXPIDITE PLAN REVIEW: WHEN RESUBMITTING, |
| | PLEASE REPLACE ONLY SHEETS |
| | WHICH HAVE CHANGED AND PROVIDE ONE COPY |
| | OF ALL OLD/VOIDED SHEETS FOR REFERENCE |
| | ONLY. NOTE: ONLY ONE CORRECTED DRAWING |
| | IN RED INK FOR REFERENCE FOR |
| | RESUBMITTAL. |
| | |
| | END OF COMMENTS: |
| | |
| | REVIEW BY MIKE PERSON |