| 2007-02-02 13:23:53 | PLEASE EXPLAIN WHAT CHANGES YOU MADE FROM LAST TIME WE |
| | APPROVED ENGINEERING ON 3-31-06?? |
| | |
| | 1. DIDYOU MAKE ANY CHANGES INSIDEWALK WIDTH , ITS |
| | SLOPE, DRIVEWAY, PARKING, HANDICAP PARKING, PAINT, ALL |
| | MUST FOLLOW CITY STANDARDS,PER CITY CODES ETC., MUST |
| | MEET PER ADA,,ETC., |
| | 2. DID YOU MAKE ANY CHANGES IN DRAWINGS FORDUMPSTER & |
| | ITS ENCLOSURE DETAILS? LOCATION ON DWG, LOCATION MUST |
| | BE ACCESSIBLE FOR PICKUP TRUCK. |
| | 3. ANY CHANGES IN FIRST FLOOR ELEVATION, CENTER LINE OF |
| | ROAD , SIDEWALK ELEVATION MUST MEET FL BLDG CODE, |
| | PLEASE SHOW ON THE DRAWINGS. |
| | 4. ANY CHANGES IN SFWMD PERMIT, OR GEO TECH REPORT?? |
| | 5.ANY CHANGES IN STORM WATER CALCULATIONS, WHAT |
| | CRITERIA YOU ASSUMEDFOR RUNOFF CAL.,, LIKE 1" OVER |
| | ENTIRE SITE OR2.5"CRITERIA, ?PERVIOUS AREA, LIKE |
| | GREEN, LAKES, ETC,IMPERVIOUS AREA CAL., |
| | 6. ANY CHANGES IN THE SITE AREA, YOU ARE DEVELOPING FOR |
| | THIS PROJECT ? SO, WE CAN CHECK PERVIOUS, IMPERVIOUS |
| | CAL. |
| | 7.ANY CHANGES IN CONNECTING THE STORM WATER PIPES IN |
| | YOUR SITE? ITS DETAILS.PLEASE SHOW ALL STORM WATER |
| | PIPES AROUND YOUR SITE SO, WE CANSEE THE BEST PIPE TO |
| | CONNECT WITH THE STORM WATERFROM ALL OTHER STORM |
| | WATER PIPES. PLEASE SHOW DETAIL OF THE CONTROL |
| | STRUCTURES WITH ELEVATIONS, NOTCHES, BLEEDING |
| | ELEVATION, ETC DID YOU USE EXFILTRATION TRENCH ? |
| | 8. ANY CHANGES IN POLLUTION PREVENTION DETAILS,CLOTHES |
| | USED FOR SILT ETC., PLANS SHOWING SILT FENCE AROUND THE |
| | SITE |
| | 9.ANY CHANGES INWATER & SEWER PLANS?MUST BE |
| | APPROVED FROM 45TH STREET (MANNY G.), UTILITY DEPT |
| | BEFORE WE APPROVED |
| | 10..ANY CHANGES IN CATCH BASINS NEAREST,AROUND YOUR |
| | SITE FOR STORM WATER DRAIN. |
| | |
| | PLEASE RESPOND EACH ITEM IN DETAIL IN A LETTER AND IN |
| | THE DRAWINGS AS REVISIONS,TO EXPEDITE YOUR PERMITTING |
| | PROCESS |
| | |
| | RASIK CHOKSHI805-6723 |