| Plan Review Notes For Permit 06010883 |
| Permit Number |
06010883 |
|
| Review Stop |
B |
| Sequence Number |
2 |
|
| Notes |
| Date |
Text |
| 2006-02-22 00:00:00 | 1801 NORTH FLAGLER DRIVE | | | POST-TENSION TENDON REPAIR/UNIT#604 | | | CONTRACTOR:DOSDOURIAN ENTERPRISES INC. | | | | | | 1)RECEIVED ADDITIONAL DOCUMENTATION AS | | | REQUESTED. | | | | | | 2)THE G/C MUST COORDINATE WITH THE | | | STRUCTURAL ENGINEER TO ENSURE THAT THE | | | NOTED REPAIRS CONFORM TO THE SUBMITTED | | | APPROVED DETAIL AND PRESCRIBED | | | PROCEDURES.REQUIRE A CERTIFICATE OF | | | COMPLETION LETTER SIGNED & SEALED BY THE | | | ENGINEER PRIOR TO A FINAL INSPECTION. |
|