| Date |
Text |
| 2006-09-22 00:00:00 | DENIED; |
| | 1ADA DETAIL FOR PHASE 11 ON PAGE A-2 |
| | ONLY SHOWS A DETAIL OF LAVATORY. DETAIL |
| | OF WHOLE BATHROOM IS REQUIRED, SHOW THE |
| | TOILET, SHOWER, AND LAVATORY IN DETAIL. |
| | REQUIREMENTS FOR COMPLIANCE CAN BE |
| | FOUND, FBC-2004 CHAPTER 11; TOILET SEC. |
| | 11-4.16.1 THRU 11-4.16.6; LAVATORY |
| | 11-4.19.1 THRU 11-4.19.6; SHOWER DETAIL |
| | SECTION 11-4.21.1 THRU 11-4.21.8. |
| | 2.HOT WATER REQUIRED TO SERVICE SINK. |
| | (SHOW ON PLANS)LOCATION SIZE AND FUIL |
| | SORCE OF WATER HEATER. |
| | 3.SANITARY RISER DIAGRAM; |
| | A)TRENCH DRAIN AND FLOOR DRAIN SHALL |
| | NOT BE DOUBLE TRAPPED. SEC.1002.1 |
| | B)WHAT IS THE 4" VERTICAL DRAIN AND |
| | BACK WATER VALVE FOR? NEED MORE |
| | INFOREMATION. |
| | C)WHY IS A FLOOR DRAIN NEEDED IN THE |
| | FUTURE PAINT BOOTH? (SECOND |
| | REQUEST) |
| | 4. SAND INTERCEPTER; (SECOND REQUEST) |
| | PLANS MUST BE REVIEW AND APROVED BY THE |
| | UTILITY DEPARTMENT FOR SIZE AND |
| | LOCATION. |
| | THE CONTACT PERSON IS; |
| | LYNN MASSON |
| | PHONE822-2271 |
| | FAX 822-2279 |
| | E-MAIL [email protected] |
| | 5.PLUMBING FIXTURE REQUIREMENT TABLE FOR |
| | PHASE 11 IS NOT CORRECT. WORK WILL BE |
| | DONE IN IN THIS PART OF THE BUILDING. |
| | PLEASE CHANGE CLASIFICATION TO BUSINESS, |
| | OR CHANGE BOTH PHASES TO BUSINESS. |
| | PLUMBING PLAN REVIEW BY; |
| | JOHN LEECH |
| | 805-6695 |
| | |