Plan Review Notes
Plan Review Notes For Permit 05121217
Permit Number 05121217
Review Stop E
Sequence Number 3
Notes
Date Text
2006-12-05 09:26:04**** UNSAT ****
  
 ** PLEASE KNOW THIS IS THE FIRST REVIEW UNDER THE NEW
 DESIGN FOR THE ELECTRICAL AND DESIGN CHANGES OF
 BUILDING WHICH CONTAINS SIGNIFICANT CHANGES FROM THE
 PREVIOUS REVIEWED PLANS.
 PLEASE KNOW THE MEETING HELD BEFORE PLANS WERE
 SUBMITTED FOR THIS REVIEW DID NOT CONSTITUTE AS A
 TECHNICAL ELECTRICAL REVIEW OF SAID PLANS.
 PLEASE KNOW SOME ITEMS FROM MEETING ALONG WITH THIS
 FULL REVIEW ARE BEING NOTED BELOW.
  
  
 1) NOTE: PLEASE SUBMIT THE MANUFACTURE SPECS/CUT SHEETS
 WHICH CORRELATE WITH THE ELECTRICAL PLANS AND RISER FOR
 THE AUTOMATIC TRANSFER SWITCH.
 PLEASE SEE THE PLANS INDICATE AN ASCO/ONAN/CUMMINS TYPE
 SWITCH HOWEVER PLEASE SEE THE SPECS SUBMITTED ARE FROM
 A COMPLETELY DIFFERENT MANUFACTURE.
 PLEASE ALSO SEE THE PLANS INDICATE THAT FACT THAT THE
 ATS SHALL NOT CONTAIN ANY BREAKER WHICH IS OK AND IS
 NOT REQUIRED, HOWEVER BASED ON THE SPEC SUBMITTED THE
 PROPOSED ATS DOES CONTAIN A BREAKER.
 PLEASE CORRELATE AND PLEASE SEE COMMENTS BELOW AS THEY
 ARE ALSO IN RESPECT TO WHAT THE PLANS INDICATE FOR THE
 ATS.
 110.3, 90.7
 FBC 106.1.2 ADMIN SECTION.
  
 ** PLEASE KNOW THAT AS THE PLANS WERE FIRST
 OVER-VIEWED, A CALLED WAS PLACED TO KAMM CONSULTING TO
 HAVE THE MANUFACTURES SPECS/CUT SHEETS E-MAILED OR
 FAXED AS IT WAS THE HOPE THAT THIS MAY HAVE BEEN THE
 ONLY COMMENT. PLEASE KNOW AS OF THIS REVIEW AND BASED
 ON THE FOLLOWING COMMENTS SUBMITTING THE CORRECTED
 SPECS UNFORTUNATELY WILL NOT HELP IN THE PROCESSING OF
 THE PLANS.
  
 2) NOTE: PLEASE CORRELATE THE PLANS, RISER AND SPEC FOR
 THE ATS. PLEASE SEE THE PLANS INDICATE THE ATS AS 1200A
 ON 4.1 AND 800A ON 5.1.
 PLEASE ALSO VERIFY THE OVER CURRENT PROTECTION TO THIS
 ATS AS THE MAIN DISTRIBUTION PANEL (MDP) SHOWS A 1000A
 BREAKER FEEDING THIS ATS WHICH IS RATED AT 800A'S OR
 WILL IT BE HIGHER?
 PLEASE CORRELATE.
 90.7, FBC 106.1.2
  
 3) NOTE: PLEASE SEE PANEL "MDP" INDICATES A 1000A
 BREAKER FEEDING THE ATS AS NOTED ABOVE, HOWEVER THE
 "GMDP" IS ONLY RATED AT 800A'S.?
 PLEASE ALSO CORRELATE AS THE PLANS ON 4.1 INDICATE THE
 "GMDP" AS 1200A'S?
 PLEASE KNOW IF THIS BREAKER AND FEED TO THE GMDP IS
 ACTUALLY GOING TO BE SIZED AT 1000A'S AT 277/480V,
 PLEASE SEE 240.13, 230.95, 700.7D, 700.26 AND NFPA-110,
 6.2.15* ISOLATION OF NEUTRAL CONDUCTORS. PROVISIONS
 SHALL BE INCLUDED FOR ENSURING CONTINUITY, TRANSFER,
 AND ISOLATION OF THE PRIMARY AND THE EPS NEUTRAL
 CONDUCTORS WHEREVER THEY ARE SEPARATELY GROUNDED TO
 ACHIEVE GROUND-FAULT SENSING.
 THIS WAS TALKED ABOUT IN THE MEETING BEFORE PLANS WERE
 RESUBMITTED AND THE CONSENSUS AND UNDERSTANDING WAS
 THAT THE OVER CURRENT PROTECTION ON THE NORMAL LINE
 SIDE OF THE GMDP WHICH IS THE FEED FROM THE MDP WOULD
 BE CHANGED TO 800A?S WHICH WOULD IN TURN NOT REQUIRED
 THE ISOLATION OF THE NEUTRAL FOR A SEPARATELY DERIVED
 SYSTEM.
 PLEASE SEE 240.12, 110.10 AND NFPA-110 6.5.1 AS THE
 SELECTIVE COORDINATION SHALL STILL BE REQUIRED TO BE
 MET.
 PLEASE CORRELATE ALL OF THE ABOVE.
 PLEASE KNOW AS THE EQUIPMENT WHICH IS REMOTELY LOCATED
 IS NOT BEING FED FROM ONE PANEL AT THAT LOCATION AS THE
 OTHER EQUIPMENT SHOWN IS, SIGNAGE WILL BE REQUIRED FOR
 EACH DISCONNECTING MEANS AT EACH LOCATIONS DENOTING
 WHERE FEED TO EACH IS PROVIDED.
 FBC 106.1.2
  
 4) NOTE: PLEASE SEE THE FAULT CURRENT CALCULATIONS
 INDICATE SERVICE ENTRANCE CONDUCTORS FIGURED INTO THE
 CALCULATIONS WHICH ARE NOT THE SAME AS THE SEC'S WHICH
 ARE SHOWN ON THE FEEDER SCHEDULE.
 PLEASE SEE 110.9, 240.4 AND FBC 106.1.2 AND CORRELATE.
  
 5) NOTE: PLEASE SEE PLANS AT THE MAIN MECHANICAL ROOM
 AND THE MECHANICAL EQUIPMENT ON THE SITE ARE SHOWING
 ALL CIRCUITING AS "GDP"? THIS IS BEING ASSUMED THIS IS
 FROM THE OLD GARAGE DISTRIBUTION PANEL DESIGNATIONS?
 PLEASE SEE AS THE DESIGNATION ON THE GMDP IS NOTING
 THESE, THERE SHOULD BE NOT DIFFERENTIATION ON THE
 DESIGNATION ON WHICH PANEL THESE SHOULD BE FED FROM.
 PLEASE CORRELATE. PLEASE SEE SHEETS E1.3 AND E4.1.
  
 6) NOTE: PLEASE CORRELATE MDP ON PLANS WITH RISER AND
 PANEL SCHEDULE. PLEASE SEE PANEL SCHEDULE FOR THE MDP
 SWITCH GEAR INDICATES THIS AS 2000A'S WITH A 2000A MCB
 GF PROTECTED BREAKER, YET PLEASE SEE E4.1 WHICH
 INDICATE THIS AS A 3000A MAIN.
  
 7) NOTE: PLEASE SEE KEYNOTE #7 ON THE LOWER RIGHT HAND
 SIDE OF E5.1 WHICH INDICATES EACH OF ELEVATORS
 DISCONNECTS RATED AT 125A'S YET THE MDP AND THE GMDP
 INDICATE 200A OVER CURRENT PROTECTION FEEDING THESE.
 PLEASE CLARIFY THIS?
 PLEASE SEE THE OCP IS BASED ON THE OCP AT THE ELEVATOR
 DISCONNECT. PLEASE SEE THE CONNECTED LOAD BEING SHOWN
 AT 119A'S. PLEASE VERIFY THE OVER CURRENT PROTECTION AS
 THE 125A DISCONNECT DOES NOT SEEMED TO BE SIZED PER THE
 OCP FROM THE MDP AND GMDP. PLEASE SEE 620.61B1, 430,
 430.33, 430.52, 430.22E ETC.
 PLEASE KNOW AS THE HP RATING FOR EACH MOTOR IS NOT
 INDICATED AND THE TYPE OF MOTOR IS NOT KNOWN
 VERIFICATION OF THESE MOTORS CAN NOT BE DONE AT THIS
 TIME.
 PLEASE SEE E3.1 OR 4.1 DO NOT SHOW THE DISCONNECTING
 MEANS ON PLANS.
  
 8) NOTE: PLEASE SEE KEY NOTE #8 WHICH INDICATE THE
 DESIGNATION OF THE BREAKER AT THE GENERATOR AS G-2, YE
 THE RISER INDICATES A G1A1-1. IS THIS THE SAME? PLEASE
 SEE THIS OVER CURRENT PROTECTION IS BEING SHOWN AS
 600A'S WHICH IS OK; HOWEVER PLEASE SEE NOTES ABOVE WITH
 RESPECT TO THE CORRELATION OF THE EPSS (EMERGENCY POWER
 SUPPLY SYSTEM).
 PLEASE BE SURE THE MANUFACTURES SPECS/CUT SHEETS
 SUBMITTED INDICATE THE VOLTAGE, AND WHERE THE OVER
 CURRENT PROTECTION AT THE GENERATOR WILL BE. ( VOLTAGE
 IS SHOWN ON RISER NOTES)
 110.3, 90.7,
 FBC 106.1.2 ADMIN SECTION.
  
 9) NOTE: PLEASE VERIFY THE FEEDERS FROM MDP TO THE ATS
 AND FROM THE ATS TO THE GMDP. PLEASE SEE NOTES ABOVE
 WITH RESPECT TO THE OVER CURRENT PROTECTION AT THE MDP
 AND WHAT THE ACTUAL INSTALLATION WILL BE. PLEASE SEE
 THAT BASED ON THE WHETHER OR NOT THE SYSTEM IS 1200A'S,
 1000A'S, 800A'S OR 600'S, THIS WILL MOST LIKELY HAVE AN
 AFFECT ON THE FEEDERS, NUMBER OF FEEDERS AND THE SIZES
 AS SHOWN. PLEASE KNOW BASED ON THE VOLTAGE DROP FORM
 THE GENERATOR LOCATION THE FEEDERS BEING INCREASED ARE
 NOT IN QUESTION. (13-413.1.ABC.1.1)
 PLEASE CORRELATE WITH ALL OF THE ABOVE AND VERIFY THE
 SIZES AS SHOWN.
 240.4, 310.16 ETC.
 FBC 106.1.2 ADMIN SECTION.
  
  
 10) NOTE: PLEASE CLARIFY THE COORDINATION OF THE
 SPEC/CUT SHEETS SUBMITTED FOR THE GENERATOR FUEL TAN
 AND WEATHER PROOF ENCLOSURE. SPECS INDICATE AS THESE
 ARE BOTH PROVIDED AND LISTED BY ONAN, YET THE RISER
 NOTES MENTIONS A "PHOENIX" PRODUCTS FOR EACH OF THE
 TWO?
 PLEASE CLARIFY.
 110.3, AND PLEASE SEE COMMENTS PERHAPS FROM MECHANICAL
 REVIEWER.
 FBC 106.1.2
  
 11) NOTE: PLEASE PLACE AND INDICATE ALL FIXTURE
 DESIGNATIONS ON SITE PLANS AND CORRELATE WITH THE
 SUBMITTED FIXTURE LEGEND. PLEASE SEE THERE ARE SOME
 FIXTURES WHICH DO NOT CONTAIN ANY DESIGNATIONS AND
 COULD NOT LOCATED THEIR SYMBOL ON THE LEGEND?
 PLEASE ALSO CORRELATE ALL CIRCUITING SHOWN ON SITE OR
 EXTERIOR LIGHTING PLANS WITH THE LIGHTING CONTROL PANEL
 DESIGNATED AS "LC-2". PLEASE SEE THERE ARE SOME
 CIRCUITS ON PLANS WHICH ARE NOT SHOWN ON THE DETAIL ON
 E0.1. PLEASE SEE SITE PLANS ETC CONTAINS NOTES TO SEE
 THE DETAIL ON E0.1, YET THESE ARE NOT SHOWN.
  
 12) NOTE: PLEASE SEE FOUNTAIN PUMP ON SITE PLANS WHICH
 IS SHOWN BEING CONNECTED TO H1, 14, 16, 18, YET THE
 PANEL SCHEDULE H1 SHOWS THESE CIRCUITS AS SPARE/BLANK.
 PLEASE COMPLETE AND CORRELATE.
 240.4, 310.16, 408.4
  
 ** ** IMPORTANT**
 ONCE ALL REVIEWS ARE DONE AND PLANS ARE
 PICKED UP FOR CORRECTIONS, PLEASE BE
 SURE TO COMPLETELY REMOVE ALL OLD/VOIDED
 SHEETS AND ONLY INSERT NEW REVISED
 SHEETS INTO TWO COMPLETE SETS FOR REVIEW
 AND STAMPING. DO NOT LEAVE ANY
 OLD/VOIDED SHEETS IN SETS.
 PLEASE KNOW ONLY ONE SET OF THE
 OLD/VOIDED SHEETS SHOULD BE SUBMITTED
 FOR REFERENCE.
 THIS WILL HELP IN THE REVIEW PROCESS AND
 AVOID ANY DELAYS.
  
 ** PLEASE BE SURE TO CALL IF THERE ARE ANY QUESTIONS OR
 COMMENTS WITH RESPECT TO THE TYPED COMMENTS ABOVE. IF
 THERE ARE ANY COMMENTS WHICH ARE NOT CLEAR IN ANY WAY,
 NOT UNDERSTOOD OR NOT TYPED IN A CLEAR MANOR, PLEASE DO
 NOT HESITATE IN CONTACTING THIS OFFICE AND THIS
 REVIEWER.
  
  
 DEWEY PALMER
 ELECTRICAL PLAN REVIEW
 CONSTRUCTION SERVICES DEPT.
 CITY OF WEST PALM BEACH
 561-805-6717
 [email protected]
  
  
  
  
2006-12-05 06:47:27REVIEW IN PROGRESS 06:45 12/5
2006-12-04 20:05:35NOTES TO FOLLOW, REVIEW STOPPED AT 8PM ON 12/4 TO
 CONTINUE ON 12/5
2006-12-03 20:49:35ONE SET IN ELECTRICAL FOR REVIEW.