| 2009-04-20 12:49:47 | PLAN FAILED. |
| | PLAN REVIEWER: DEAN LAUDERMILK, ENG. SRVC. # |
| | 561-494-1083, CONSTR. SRVC. # 561-805-6716 |
| | 1. CIVIL PLAN HAS NOT BEEN RESUBMITTED TO ENGINEERING |
| | SERVICES SINCE THE PLANS WERE APPROVED ON MARCH 3, |
| | 2006. CIVIL PLAN IS ONLY APPROVED FOR A PERIOD OF 1 |
| | YEAR AND THAT IS ONLY IF NO REVISIONS HAVE BEEN MADE. |
| | SOME SHEETS HAVE OVER 10 REVISIONS MADE FROM 04-21-06 |
| | TO 01-14-09. PLUMBING PLAN SHOWS TWO SUMP PUMPS SERVING |
| | THE TRUCK SCALES ARE TIED TO THE BUILDINGS SANITARY |
| | SEWER SYSTEM, WHILE THE CIVIL SHEETS (5' OUTSIDE THE |
| | BUILDING) SHOW NO CHANGES TO THE SANITARY. RESUBMIT A |
| | MINIMUM OF FOUR FULL SETS OF CIVIL DRAWINGS TO |
| | ENGINEERING SERVICES FOR REVIEW. TWO OF THE SETS WILL |
| | BE RETURNED. IF MORE ARE REQUIRED (FOR PERMITTING) THEN |
| | SUPPLY MORE THAN 4 SETS. SEE ITEM 2 WHICH NEEDS TO BE |
| | SHOWN ON THE CIVIL PLANS. |
| | |
| | 2. P-10 HAS A REVISION TO ALLOW TWO SUMP PUMPS TO BE |
| | INSTALLED TO PUMP (WHAT?) INTO THE BUILDINGS INTERIOR |
| | GRAVITY SYSTEM AND OUT INTO THE CITY'S SYSTEM. THERE IS |
| | NOT ENOUGH DETAIL IN THE PLANS TO SHOW PROOF THAT THE |
| | BUILDING IS WATER TIGHT AND NO RAIN WATER WILL GET INTO |
| | THE SYSTEM. THE ONLY WAY THIS SYSTEM CAN BE TIED TO THE |
| | CITY SYSTEM IS IF THE AREA IS ROOFED AND NO RAIN WATER |
| | CAN BE TRANSPORTED INTO THE SANITARY SEWER. THEN THE |
| | LIQUID WILL NEED TO GO VIA A WATER/OIL SEPARATOR |
| | (GREASE TRAP) AND THEN IT CAN BE DIRECTED TO THE CITY |
| | SYSTEM. THIS NEEDS TO BE SHOWN ON THE CIVIL PLAN SHEET |
| | SINCE IT IS OUTSIDE THE BUILDING FOOT PRINT. |