| Date |
Text |
| 2006-02-10 00:00:00 | ******** UNSAT *********** |
| | |
| | |
| | 1)NOTE: PLEASE SEE NEW RISER IS NOW |
| | SHOWING A 200A DISCONNECT, DOES THIS |
| | CONTAIN OCP AS REQUIRED? |
| | PLEASE ALSO SEE THIS NEW 200A DISCONNECT |
| | AS IT IS FEEDING A 150A PANEL WITH 150A |
| | FEEDERS? |
| | PLEASE VEIRFY IF THIS 200A DISCONNET |
| | CONTAINS EITHER 150A BRKR, OR 150A FUSES |
| | ETC.? |
| | PLEASE ALSOSEE NEW ATS WITH 200A OCP IS |
| | ALSO SHOWN FEEDING A 150A PANEL AND |
| | FEEDERS WITH 200A OCP. |
| | 240.4,310.16,240, 230.70 215.5 |
| | |
| | 2)NOTE: PLEASE PROVIDE AIC RATINGS FOR |
| | ALL NEW SERVICE EQUIPMENT PER 110.9, |
| | 215.5 |
| | |
| | 3)NOTE: PLEASE PROVIDE AND SUBMIT LOAD |
| | CALCULATIONS. PLEASE SEE RISER MENTIONS, |
| | LOAD IS @ 125A'S, HOWEVER GENERATOR IS |
| | ONLY RATED @ 112A'S PER NG 27KW RATING. |
| | PLEASE KNOW, DERATING MAY BE TAKEN FOR |
| | NORMAL GEHN/LTS RECEPTS ETC, HOWEVER |
| | 100% SHALL BE FIGURED FOR CONNECTED |
| | MOTOR, A/C, AND A/C HEAT LOADS UNLESS |
| | SOME MEANS OF LOAD SHEDDING IS PROVIDED. |
| | 220,702.5,215.5 |
| | |
| | 4)NOTE: PLEASE SEE EXISTING SERVICE |
| | SEEMED TO INDICATE A 300A |
| | SERVICE,HOWEVER AS SHOWN, RISER HAS NOW |
| | INCREASED THIS TO 400A'S? HAS METER |
| | CHANGED? WHAT SIZE IS METER? |
| | PLEASE ALSO VERIFY EXISTING GROUNDING |
| | ELECTRODE SYSTEM AND SIZE OF EXIST. |
| | IF SERVICE DOES INCREASE THEN GEC SHALL |
| | BE REQUIRED TO BE INCREASED BASED ON |
| | TABLE FROM 250.66 |
| | |
| | 5)NOTE: PLEASE SEE NOC RECORDED HAS |
| | SINCE EXPIRED AND WILL BE REQUIRED TO BE |
| | RE-RECORDED AS REQUIRED UNDER |
| | FS713.13(2). WORK HAS NOT COMMENCED |
| | WITHIN 90 DAYS OF RECORDING , THE NOC |
| | SHALL BECOME VOID. |
| | |
| | PLEASE SUBMIT THE ABOVE INFORMATION FOR |
| | REVIEW. IF THERE ARE ANY QUESTIONS, |
| | PLEASE DO NOT HESITATE IN CONTACTING |
| | THIS OFFICE. |
| | |
| | DEWEY PALMER |
| | ELECTRICAL PLAN REVIEW |
| | 561-805-6717 |
| | [email protected] |