| 2009-02-20 14:04:24 | ** DENIED REVIEW ** |
| | |
| | |
| | |
| | ** THE FOLLOWING REVIEW NOTES WERE POSTED AND ARE |
| | PARTIALLY ON HOLD FOR THE ISSUES BELOW AND SITE |
| | LIGHTING PERMITTING ISSUES. |
| | SPOKE TO DESIGNER FROM KAMM CONSULTING AT LENGTH WITH |
| | RESPECT TO PERMITTING OF SITE AND THE FACT SHEETS E.01 |
| | AND 5.1 WHICH ARE IN THE SETS ARE NOT THE CORRECT |
| | SHEETS. |
| | THE SITE LIGHTING WAS ONLY APPLIED FOR PERMIT IN |
| | FEBRUARY 2009. THIS IS TWO CODE CHANGES/REVISIONS PAST |
| | ORIGINAL NOVEMBER 2005 PERMIT APPLICATION DATE. |
| | THE PARKING STRUCTURE WAS APPLIED FOR PERMIT IN AUGUST |
| | OF 2007. IF SITE LIGHTING IS ATTACHED TO THAT STRUCTURE |
| | PERMIT, LIGHTING WOULD STILL NEED TO MEET PRESCRIPTIVE |
| | REQUIREMENTS OF THE LIGHTING AT THAT TIME. |
| | THE ONLY WAY TO USE THE BUILDING ALLOWANCES AS TRADE |
| | OFFS FOR SITE LIGHTING WOULD BE TO REVISE THE BASE |
| | BUILDING PERMIT TO INCLUDE ALL SITE LIGHTING. THE SITE |
| | LIGHTING WOULD MOST LIKELY EXCEED THE PRESCRIPTIVE |
| | REQUIREMENTS UNDER THE CURRENT CODE OR EVEN UNDER THE |
| | PRESCRIPTIVE OF 2007. KEEP IN MIND METHOD *A* IS FOR |
| | WHOLE BUILDING BY DEFINITION FOR ALL KNOWN COMPONENTS |
| | NOT ONLY THE ONES CURRENTLY UNDER PERMIT WITHOUT FIRE |
| | WALL SEPARATION. |
| | IN DOING SO THIS WOULD NOT PERMIT THE BASE BUILDING TO |
| | OBTAIN A C OF C OR C OF O. ALL SITE LIGHTING WOULD NEED |
| | TO BE COMPLETE BEFORE THE FINALS COULD BE COMPLETED. |
| | THIS WOULD EXTEND THE 05 PERMIT UNTIL ALL WORK IS |
| | COMPLETED. |
| | |
| | |
| | ** ORIGINAL COMMENTS ON REVISIONS: BRAMAN MOTORS |
| | THESE WERE GONE OVER AT LENGTH WITH DESIGNER FROM KAMM. |
| | |
| | |
| | 1) NOTE: PLEASE SEE SHEET E0.1. THIS SHEET IS LABELED |
| | FOR PHASE II SCOPE OF WORK. THIS SHEET HAS NOW BEEN |
| | COMPLETELY REVISED REMOVING A SUBSTANTIAL AMOUNT OF |
| | INFORMATION WHICH WAS ON PREVIOUS RECORD SET OF PLANS. |
| | THERE IS NEW INFORMATION AND DETAILS. IF THIS SHEET IS |
| | NOT SUPPOSE TO BE IN THIS SET WHY IS IT MARKED PHASE II |
| | WHICH IS THIS PERMITTED SCOPE OF WORK? |
| | WHERE IS THE ACTUAL REVISED E0.1 NEEDED? |
| | THIS INFORMATION IS REQUIRED AND NEEDED ON THE PLANS IN |
| | ORDER TO REVIEW FOR CODE COMPLIANCE. IT WAS THOUGHT |
| | THAT PERHAPS THAT SOME OF THE PREVIOUS INFORMATION WAS |
| | PLACED ON OTHER SHEETS HOWEVER THIS INFORMATION IS NOT |
| | LOCATED ON ANY OF THE OTHER PLANS SUBMITTED. SEVERAL OF |
| | THESE ITEMS WILL BE NOTED BELOW. |
| | |
| | A) THE CORRECT YEARS FOR THE CODES ARE NOW REMOVED. |
| | NFPA-70, NFPA-101, NFPA-72 NOW DOES NOT HAVE ANY LISTED |
| | ADOPTED EDITIONS LISTED WHICH WAS ON RECORD PLANS. |
| | SHOULD BE: |
| | 2002 NFPA-70 |
| | 2003 NFPA-101 |
| | 2002 NFPA-72 |
| | |
| | B) THE SHEET E0.1 IS NOW MISSING THE FIXTURE LEGEND |
| | WHICH IS NEEDED TO REVIEW AND COORDINATE FIXTURES ON |
| | PLANS FOR CHAPTER 13 COMPLIANCE WITH RESPECT TO ENERGY |
| | CALCULATIONS. |
| | THERE WERE PREVIOUS COMMENTS SPECIFIC TO THE PREVIOUSLY |
| | REVISED E0.1 HOWEVER THIS SHEET NOW IN SETS DOES NOT |
| | EVEN COORDINATE WITH THE RESPONSE FROM THE DESIGNER. |
| | 13-415.2, 13-415.2.ABC.1.1,.1.2 AND .1.3. |
| | |
| | C) THE REVISED NEW SHEET E0.1 NOW HAS THE SYMBOL LEGEND |
| | REMOVED. THIS IS PART OF THIS REVISED SHEET E0.1 WHICH |
| | SHOULD OR SHOULD NOT BE IN THE SET. |
| | |
| | |
| | 2) NOTE: THERE IS ALSO A REVISED/NEW SHEET E5.1 WHICH |
| | IS NOT ACCURATE FOR THIS SCOPE OF WORK. IT IS LABELED |
| | PHASE II WHICH IS WHAT IT IS SUPPOSED TO BE LABELED |
| | HOWEVER THE SHEET DOES NOT CONTAIN THE CURRENT SCOPE OF |
| | WORK. WHERE IS THE REVISED SHEET 5.1 WHICH WAS |
| | ADDRESSING THE PREVIOUS COMMENTS? |
| | |
| | THE ACTUAL REVIEW OF SEVERAL ITEMS CAN NOT BE DONE |
| | UNTIL THE REVISED PLANS ARE IN SETS FOR REVIEW. OTHER |
| | SHEETS WHICH DO NOT HAVE COMMENTS AT THIS TIME SHOULD |
| | BE SUBMITTED BACK WITH OTHER CORRECTED/REVISED SHEETS. |
| | THESE ARE: |
| | 2.1.1, 2.1.2, 3.1.1, 3.1.2, 6.1,6.2 AND 7.1. |
| | |
| | |
| | |
| | ** IMPORTANT ** |
| | ONCE AUDIT/REVIEWS ARE COMPLETE AND PLANS ARE PICKED UP |
| | FOR CORRECTIONS, PLEASE BE SURE TO COMPLETELY REMOVE |
| | ALL OLD/VOIDED SHEETS AND ONLY INSERT NEW REVISED |
| | SHEETS INTO TWO COMPLETE SETS FOR REVIEW AND STAMPING. |
| | DO NOT LEAVE ANY OLD/VOIDED SHEETS IN SETS. |
| | PLEASE DO NOT ATTACH SUPPORTING DOCUMENTS TO PLANS. ANY |
| | ADDITIONAL DOCUMENTATION SUCH AS PRODUCT APPROVALS, |
| | SPEC/CUT SHEETS, CALCULATIONS ETC. SHOULD BE PLACED |
| | INTO TWO SETS/FOLDERS/BINDERS ETC. |
| | PLEASE KNOW ONLY ONE SET OF THE OLD/VOIDED SHEETS |
| | SHOULD BE SUBMITTED FOR REFERENCE. |
| | THIS WILL HELP IN THE AUDIT/REVIEW PROCESS AND AVOID |
| | ANY DELAYS. |
| | |
| | IF THERE ARE ANY QUESTIONS; OR IF COMMENTS ARE NOT |
| | TYPED IN A CLEAR MANNER PLEASE DO NOT HESITATE TO |
| | CONTACT THIS REVIEWER. |
| | |
| | DEWEY PALMER |
| | ELECTRICAL PLAN REVIEW II |
| | CONSTRUCTION SERVICES DEPARTMENT |
| | CITY OF WEST PALM BEACH |
| | 561-805-6717 |
| | [email protected] |
| | |