Plan Review Notes
Plan Review Notes For Permit 05110803
Permit Number 05110803
Review Stop M
Sequence Number 2
Notes
Date Text
2006-10-12 12:16:50***************SHELLONLY***************
 BUILDING B:
  
 RESPONSE TO COMMENTS FROM REVIEW DATED 2-2-06:
  
 COMMENT 1:REPONSE INDICATES PER OUR CONVERSATION
 METHOD A ENERGY CALCULATIONS WILL BE SUBMITTED WITH
 SPEPARATE BUILD OUT PERMIT.PER 2004 FBC CHAPTER 13
 SUB-CHAPTER 13-101.1.1, NEW CONSTRUCTION COMEERCIAL
 BUILDINGS SHALL COMPLY WITH SUBCHAPTER 13-4.METHOD B,
 BUILDING, ENVELOPE TRADE-OFF METHOD IS REQUIRED FOR
 SHELL BUILDINGS.THE METHOD A WILL BE REQUIRED FOR THE
 BUILD-OUT PERMIT.THIS WAS ALSO A COMMENT BY THE
 BUILDING PLANS EXAMINER.
  
 PLAN SHEET M-1B
 SCOPE OF MECHANICAL WORK TO BE DONE UNDER THE SHELL
 PERMIT IS AS FOLLOWS:
 1.DUCTLESS SPLIT UNIT TO THE ELEVATOR EQUIPMENT ROOM
 2.OUTDOOR INTAKES & EXHAUST LOUVERS, EXTENDING 12"
 INTO BUILDING & CAPPED OF FUTURE.
  
 PLEASE NOTE, PVC REFRIGERANT RISER SHALL NOT BE A PASS
 THROUGH ANY FUTURE PLENUMS.
  
 COMMENT 2 & 3 WERE ADDRESSED.
  
 ***NEW COMMENT****
 ADDITIONAL MECHANICAL PERMIT REQUIRED FOR THE BUILDOUT
 PLAN SHEET M-1B INDICATES CONDENSING UNITS,PLEASE
 NOTE CLEARANCES SHALL BE NO LESS THAN MANUFACTURER'S
 RECOMMENDATIONS AND SUFFICIENT TO ALLOW INSPECTIONS,
 SERVICE REPAIR OR REPLACEMENT PER 2004 FMC 306.1.