| 2007-02-09 18:54:53 | REVISION DENIED |
| | REFERENCE: FBC-2004 PLUMBING |
| | FBC-2004 FUEL GAS |
| | FBC-2004 CHAPTER 1 |
| | |
| | 1. SHT P-1 HAND DRAWN CHANGES AND WHITE OUT ARE NOT |
| | APPROVED FOR REVISIONS. SECTION 106.1.3.--NO CHANGE |
| | NOTED ON ONE REVISION #5< (BETWEEN COL. LINE 11 & 12). |
| | --PLEASE TURN OFF THE CLOUDS AND NUMBERED TRIANGLES |
| | FROM PREVIOUS REVISIONS TO EXPEDITE REVIEW OF THE |
| | REVISIONS. SECTION 106.1.1. |
| | |
| | 2. SHT P-5 HAND DRAWN CHANGES AND WHITE OUT ARE NOT |
| | APPROVED FOR REVISIONS. SECTION 106.1.3.--PLEASE |
| | TURN OFF THE CLOUDS AND NUMBERED TRIANGLES FROM |
| | PREVIOUS REVISIONS TO EXPEDITE REVIEW OF THE REVISIONS. |
| | SECTION 106.1.1. |
| | |
| | 3. SHT P-8WHITE OUT IS NOT APPROVED FOR REVISIONS. |
| | SECTION 106.1.3.--PLEASE TURN OFF THE CLOUDS AND |
| | NUMBERED TRIANGLES FROM PREVIOUS REVISIONS TO EXPEDITE |
| | REVIEW OF THE REVISIONS. SECTION 106.1.1. |
| | |
| | 4. SHT P-9WHITE OUT IS NOT APPROVED FOR REVISIONS. |
| | SECTION 106.1.3.--PLEASE TURN OFF THE CLOUDS AND |
| | NUMBERED TRIANGLES FROM PREVIOUS REVISIONS TO EXPEDITE |
| | REVIEW OF THE REVISIONS. SECTION 106.1.1. |
| | |
| | 5. SHT P-10 SHOWS THE DRAINAGE FROM (L-11) 4" ROOF |
| | DRAIN 824 SQ FT BEING ROUTED TWO DIFFERENT WAYS TO THE |
| | RISER. PLEASE CLARIFY. SECTIONS 106.1.1 AND 706.3. |
| | |
| | 6. SHT P-15THE GAS RISER DIAGRAM BETWEEN SECTIONS (1) |
| | & (2) DO NOT REFLECT THE GAS EQUIPMENT SCHEDULE. THE |
| | RISER SHOWS TWO ITEM 45'S AND THE SCHEDULE ONLY SHOWS |
| | ONE ITEM 45. THIS WOULD CHANGE THE TOTAL CONNECTED GAS |
| | LOAD BY 140,900 BTU'S. PLEASE CORRELATE THE RISER |
| | DIAGRAM WITH THE GAS EQUIPMENT SCHEDULE. SECTION |
| | 106.1.1. |
| | |
| | REVIEW BY KEN STEVENS |
| | (561) 805-6721 |
| | FAX (561) 805-6731 |
| | E-MAIL [email protected] |