| Date |
Text |
| 2006-08-23 00:00:00 | PROVISO: |
| | RESPONSE TO COMMENT #3:ELEVATION |
| | PROVIDED ON PLAN SHEET AC-5.PLEASE |
| | NOTE, EXHAUST FROM EF-23 SHALL NOT |
| | TERMINATE IN A MANNER THAT NOXIOUS |
| | CONTAMINANTS MY BE DRAWN BACK INTO THE |
| | FRESH AIR INTAKE (INTAKE LOUVER). |
| | PLEASE PROVIDE CO SENSOR IN THIS ROOM. |
| | |
| | RESPONSE TO COMMENT #11: PLAN SHEET AC-4 |
| | VENTLATION FOR THE POOL EQUIPMENT ROOM |
| | #1 MAKE-UP AIR AND THE EXHAUST AIR WILL |
| | BE INTO THE GARAGE.PLEASE PROVIDE CO |
| | SENSOR IN THIS ROOM. |
| | |
| | PLAN SHEET AC-7 TERMINATION OF EF-12 IS |
| | WITHIN 3FT THE POOL EQUIPMENT ROOM #2. |
| | PER 2001 FMC 401.5 OPENING LOCATION FOR |
| | EXHAUST AND INTAKES SHALL BE LOCATED A |
| | MINIMUM OF 10 FT FROM BUILDINGS ON THE |
| | SAME LOT. |
| | |
| | RESPONSE TO COMMENT #19:INIDCATES |
| | GYPSUM BOARD OVER EXPOSED SURFACES OF |
| | THE DOOR.THIS IS NOT ACCEPTABLE. |
| | PLEASE PROVIDE SOLUTION / SUBMITTAL |
| | WITHIN 60 DAYS OF THE PERMIT ISSUANCE. |
| | |
| | COMMENT 20:THE FOLLOWING RESIDENTIAL |
| | HEAT PUMPS AC-7 & AC-8 ARE REQUIRED TO |
| | HAVE FAN SHUTDOWN BY DUCT SMOKE DETECTOR |
| | OR BY AREA SMOKE DETECTORS PER 2001 FMC |
| | 606.2.1 & 606.4. |
| | |
| | IF YOU HAVE ANY QUESTIONS, PLEASE |
| | CONTACT PATTY KRAUSS AT (561)805-6719. |