| Date |
Text |
| 2005-11-08 00:00:00 | ****CORRECTIONS**** |
| | 05090646 AND 05090647 |
| | |
| | SAMANTHA HILL, BUILDING PLANS EXAMINER |
| | 561-805-6724 [email protected] |
| | |
| | |
| | 1.)A NOTICE OF COMMENCEMENT MUST BE |
| | FILED WITH THE CLERK OF COURTS BEFORE A |
| | PERMIT CAN BE ISSUED. |
| | |
| | 2.)UNDER WHICH CODE HAS THIS PROJECT |
| | BEEN DESIGNED?FBC2001 OR FBC2004? |
| | SPECIFY ON THE PLAN.THIS COMMENT LIST |
| | CANNOT REFER TO SPECIFIC CODE SECTIONS |
| | AS THIS HAS NOT YET BEEN DETERMINED. |
| | |
| | 3.)THE FIRE PROTECTION SYSTEM IS TO BE |
| | DESIGNED BY A FIRE PROTECTION SYSTEM |
| | DESIGNER, FS553.79(6)(C), FAC61G15-32. |
| | SOMEONE HAS WRITTEN ?PRE ENGINEERED? ON |
| | THE SPECIFICATION SHEETS, AND MADE |
| | REFERENCE TO UL1245.THIS IS A TEST |
| | STANDARD, NOT A LISTING.ONE SET HAS |
| | BEEN RETAINED. |
| | |
| | 4.)THE SITE PLAN IS NOT CLEAR.IS |
| | THE PAINT SPRAY BOOTH INSIDE OF THE |
| | BUILDING?THE ORIGINAL SITE PLAN HAS |
| | BEEN ALTERED.IF IT IS OUTSIDE, PROVIDE |
| | WIND DESIGN AND ANCHORING INFORMATION |
| | FBC16. |
| | |
| | 5.)PROVIDE INFORMATION IN REGARDS TO |
| | THE BOOTH.CONSTRUCTION MATERIALS, |
| | CONNECTIONS, ETC. |
| | |
| | 6.)DECLARE OCCUPANCY FOR THE EXISTING |
| | STRUCTURES, THE PREP STATION AND THE |
| | PAINT BOOTH.FBC3.SHOW OCCUPANCY |
| | SEPARATION IF APPLICABLE. |
| | |
| | 7.)WHERE IS THE PAINT STORED?PROVIDE |
| | GALLONS, TYPE, ETC. TO ASSIST IN |
| | DETERMINING OCCUPANCY, SEE H AND S |
| | OCCUPANCIES. |
| | |
| | 8.)ARE YOU USING LP OR NATURAL GAS? |
| | BOTH ARE SHOWN ON THE PLAN.WHAT IS |
| | THIS FOR? |
| | |
| | 9.)SHEET 2 OF 6, PLAN VIEW, REFERS TO |
| | CLASSES AND DIVISIONS.WHAT IS THE CODE |
| | REFERENCE FOR THIS?INFORMATION ON THE |
| | PLAN IS TO BE SPECIFIC, AND CANNOT REFER |
| | TO CODE ONLY, ESPECIALLY CODES WHICH ARE |
| | NOT GOVERNING CODE FOR THIS PROJECT, FBC |
| | CHAPTER 1. |
| | |
| | 10.)THE PRINTED NAME AND LICENSE |
| | NUMBER OF THE PERSON SEALING THE PLAN IS |
| | TO BE ON THE DOCUMENT, FAC61G15-23.002. |
| | |
| | 11.)PROVIDE A PENETRATION DETAIL FOR |
| | THE EXHAUST AND INTAKE. |
| | |
| | 12.)THE CONNECTIONS FOR THE PLENUM, |
| | SHEET 3, IS TO BE DONE ?BY OTHERS?. |
| | PROVIDE A DETAIL. |
| | |
| | 13.)SHOW THE DOOR DIMENSION, FBC10. |
| | |
| | 14.)A PLAN WAS SHOWN FOR THE PAINT |
| | BOOTH, BUT NOT FOR THE PREP STATION.IT |
| | APPEARS THAT ONE SIDE OF THE PREP |
| | STATION IS OPEN, IS THAT CORRECT?IF |
| | NOT, SHOW EXIT DOOR ON THE PLAN. |
| | |
| | 15.)SHOW EXITING INFORMATION, SEE |
| | FBC10. |
| | |
| | NOTE ? NOT ENOUGH INFORMATION ON THE |
| | PLAN TO DETERMINE CODE COMPLIANCE. |
| | |