| Date |
Text |
| 2005-10-04 00:00:00 | DENIED; | | | 1. SHOW TYPE OF PIPING MATERIAL BEING | | | INSTALLED, ALL PIPE SIZES, (AND THE EDH | | | NUMBER OF CORRUGATED STAINLESS STEEL | | | TUBING FOR EACH PIPE SIZE BEING USED. | | | 2. BTU LOAD OF EACH APPLIANCE AND THE | | | TOTAL BTU LOAD ON THE SYSTEM. REFER TO | | | THE FBC-2001 FUEL GAS CODE SECS. 401.8 | | | THRU 402.5.2 AND TABLES 402(1) THRU | | | 402(34). | | | 3. SHOW THE DISTANCE FROM THE POINT OF | | | DELIVERY, (TANK), TO THE MOST REMOTE | | | OUTLET IN THE BUILDING AND/OR SYSTEM PER | | | FBC-2001 FUEL GAS CODE APPENDIX A - USE | | | OF CAPACITY TABLES (A)(3). | | | 4.WHERE IS SECOND STAG REGULATOR? | | | GAS PLAN REVIEW BY; | | | JOHN LEECH | | | 805-6695 | | | |
|