| Date |
Text |
| 2005-12-06 00:00:00 | *** UNSAT *** |
| | |
| | 1)NOTE: PLEASE SUBMIT TWO COMPLETE SETS |
| | OF PLANS, SPECS/MANUFACTURE CUT SHEETS. |
| | PLEASE BE SURE ALL PLANS CONTAIN THE |
| | PRINTED NAME AND SIGNATURE OF THE PERSON |
| | RESPONSIBLE FOR PLANS/ DESIGN. |
| | FBC 104.2.1 ADMINISTRATIVE SECTION. |
| | |
| | 2)NOTE: PLEASE SEE PANEL SCHEDULE/LOAD |
| | CALCULATIONS SUBMITTED INDICATE FOR |
| | PANEL "A", HOWEVER RISER DIAGRAM SHOWS |
| | PANEL "B" AS THE EM PANEL? |
| | PLEASE CORRELATE. |
| | |
| | |
| | 3)NOTE: PLEASE SEE LOAD CALCUALTIONS |
| | EXCEED RATING OF DISCONNECTS FOR |
| | GENERATOR AND SERVICE. |
| | PLEASE SEE LOAD FOR PANEL. |
| | 215.5 |
| | |
| | 4)NOTE: PLEASE SEE PERMIT APPLICATION |
| | HAS NOW BEEN CHANGED BACK TO NATURAL |
| | GAS, HOWEVER PLEASE SEE SPECS FOR |
| | GENERATOR INDICATE THIS AS LP? |
| | PLEASE ALSO VERIFY WHICH, AS GEN IS NOT |
| | RATED AT 40KW AS NG. |
| | 215.5 |
| | |
| | ** PLEASE NOTE** |
| | AUTOMATIC LOAD SHEDDING MAY BE AN |
| | OPTION. |
| | |
| | |
| | PLEASE SUBMIT THE ABOVE INFORMATION FOR |
| | REVIEW. PLEASE ALSO BE SURE TO SUBMIT |
| | "2" SETS OF PLANS TOGETHER. |
| | |
| | IF THERE ARE ANY QUESTIONS, PLEASE DO |
| | NOT HESITATE IN CONTACTING THIS OFFICE. |
| | |
| | ** PLEASE SEE THE NOC SHOWN IS FOR THE |
| | BLD CONTRACTOR AND FOR THE NEW SFR. A |
| | SEPARATE NOC WILL BE REQUIRED AS THE NEW |
| | SFR DOES NOT INCLUDE THE GENERATOR.FS |
| | 713.13(2) |
| | |
| | DEWEY PALMER |
| | ELECTRICAL PLAN REVIEW |
| | 561-805-6717 |
| | [email protected] |