Plan Review Notes
Plan Review Notes For Permit 05070627
Permit Number 05070627
Review Stop E
Sequence Number 2
Notes
Date Text
2005-12-28 00:00:00********** UNSAT 2ND REVIEW **********
  
 ** PLEASE SEE THERE ARE NOTES FROM
 ORIGINAL REVIEW WHICH STILL NEED TO BE
 ADDRESSED.
 ** PLEASE SEE SOME NEW NOTES DUE TO
 CHANGES MADE TO PLANS, AND ITEMS BEING
 REMOVED FROM SAID DRAWINGS.
  
 ** PLEASE SEE FIRST PART OF NOTES BELOW
 HAVE BEEN TAKEN DIRECTLY FROM PREVIOUS
 REVIEW.
  
  
 1)NOTE: NOTE #1 NO,
 PLEASE SEE MISSING INFORMATION REQUIRED
 ON TITLE BLOCK FOR ENGINEERING FIRM.
 PLEASE SEE 61G15-23.002 FOR MISSING
 PRINTED NAME AND PRINTED LICENSE # FOR
 ENGINEER.
 PLEASE SEE ARCHITECTS TITLE BLOCK FOR
 ALL SHEETS SHALL ALSO CONTAIN THE
 PRINTED NAME AND LICENSE # FOR ARCH.
 61G1-16.004
  
 THIS SEE THIS IS REQUIRED FOR ALL SHEETS
 AND FOR ALL TRADES WHETHER OR NOT
 COMMENT IS MADE BY OTHER REVIEWER(S).
  
 2)NOTE: NOTE #2 OK.
  
  
 3)NOTE: NOTE#3 NO, PLEASE SEE MOST
 CIRCUITING IS NOW SHOWN ON PLANS,
 HOWEVER SOME STILL APPEAR TO BE MISSING.
 PLEASE SEE NEW NOTES PERTAINING TO SOME
 ERRORS IN CIRUITING AND CORRELATION WITH
 PANEL SCHEDULES ETC.
 **
 PLEASE SHOW ALL CIRCUITING ON
 PLANS AND CORRELATE WITH PANEL
 SCHEDULES.
 PLEASE SEE ALL CONTROL WIRING FOR
 LIGHTING PLANS.
 PLEASE SEE LIGHTING PLANS DO NOT SEEM TO
 BE COMPLETE AT THIS TIME?
 PLEASE SEE SOME AREAS DO NOT INDICATE
 ANY LIGHTING? WOMENS RESTROOM?
 PLEASE SEE THIS MAINLY SEEMS TO BE
 MISSING FROM LIGHTING PLANS.
 **PLEASE ALSO SEE CIRCUTING FOR A/C
 SYSTEMS, PANELS TEND TO BE INDICATED ,
 HOWEVER NOT THE CIRCUITING.
  
 4)NOTE: OK, HOWEVER SEE NOTE #5, AS
 AREAS NEED TO BE VERIFIED FOR EGREE ETC.
 SEE NEW NOTES>
 **
 PLEASE SEE 700.12E FOR CIRCUITING
 OF EM/EXT LTS. THE BRANCH CIRCUIT
 FEEDING THE UNIT EQUIPMENT SHALL BE THE
 SAME BRANCH CIRCUIT AS THAT SERVING THE
 NORMAL LIGHTING IN THE AREA AND
 CONNECTED AHEAD OF ANY LOCAL SWITCHES.
  
 5)NOTE: NOTE #5, NO, INFACT ALL OF THE
 AREAS AND ROOM DESIGNATIONSWHICH WERE
 SHOWN ON ORIGINAL PLANS HAVE NOW BEEN
 REMOVED MAKING IT IMPOSSIBLE TO REVIEW
 SOME THINGS FOR CODE COMPLIANCE. PLEASE
 SEE NEW COMMENTS.
 **
 PLEASE INCLUDE ROOM/AREA
 DESIGNATIONS ON PLANS. THIS SHOULD BE ON
 ALL SHEETS.
 215.5
  
 6)NOTE: NOTE #6 OK.
  
  
 7)NOTE: NOTE #7 OK,NO, AS THIS AREA HAS
 NOW BEEN REMOVEDFROM PLANS AND THE KE
 PLANS NOW MENTIONS CIRCUITING.
 PLEASE SEE KE PLANS WHICH MENTIONS THESE
 ARE PRELIMINARY PLANS AND SHOULD NOT BE
 USED??
 **
 PLEASE SHOW ALL CIRCUITING ON
 KITCHEN ELECTRICAL PLAN FOR ALL. PLEASE
 CORRELATE THIS WITH EQUIPMENT SCHEDULE
 SUBMITTED AND PANEL SCHEDULES.
  
 8)NOTE: NOTE #8 NO,IT IS UNCLEAR WHERE
 ANY CHANGES HAVE BEEN MADE FOR THIS.
 PLEASE SEE NOTE #5 MENTIONS GFI FOR
 UTILITY OUTLETS?
 **
 PLEASE SEE 2002 NEC 210.8B3 FOR
 KITCHENS IN OTHER THAN DWELLING UNITS
 WHICH REQUIRES ALL 15- AND 20-AMPERE,
 125-VOLT RECEPTACLES IN NONDWELLING-TYPE
 KITCHENS TO BE GFCI PROTECTED. THIS
 REQUIREMENT APPLIES TO EACH AND EVERY
 15- AND 20-AMPERE, 125-VOLT KITCHEN
 RECEPTACLE, WHETHER OR NOT THE
 RECEPTACLE SERVES COUNTERTOP APPLIANCES.
  
  
 9)NOTE: NOTE #9 NO?? SEE NOTES WITH
 RESPECT TO ROOM AND AREA DESIGNATIONS
 BEING REMOVED.
 **
 PLEASE SHOW AND INDICATE ELEVATOR
 EQUIPMENT ROOM. PLEASE SEE
 STATE ELEVATOR CODE , NO OTHER EQUIPMENT
 UNLESS PART OF THE DESIGNATED ELEVATOR
 EQUIPMENT SHALL BE IN ELEVATOR ROOMS.
 PLEASE SEE 620.23,620.24, PLEASE VERIFY
 AND SHOW IF THESE ARE TO BE NEW OR
 EXISTING.
  
 10)NOTE: NOTE #10 NO, SAME AS PREVIOUS
 NOTES. PLEASE ALSO SEE NFPA-101 7.8.1.3,
 7.9.2 WHICH MAY ALSO BE USED IN
 REFERENCE IN THESE AREA NEED ING BATTERY
 BACK UP FIXTURES.
 **
 PLEASE SEE 700.16 FOR
 ELECTRICAL RMS, EQUIPMENT RMS, ELEVATOR
 RMS.
  
 11)NOTE: NOTE # 11, NO , UNCLEAR AS A
 "KEYED NOTE" ON RISER (NOTE #1 ON 5.1
 MENTIONS PANEL "D" WAS NOT ABLE TO BE
 LOCATED FOR WHERE FEED COMES FROM,,ETC.
 PLEASE KNOW, IT WAS DICUSSED WITH
 ENGINEER OF RECORD THIS WOULD BE A
 "PROVISO" IN WHICH THE INFORMATION WOULD
 BE REQUIRED BEFORE ANY INSPECTIONS WERE
 MADE.
 PLEASE KNOW AT THAT TIME IT WAS
 IMPERATIVE TO START PROJECT SO THIS WAS
 AGREED. PLEASE SEE RISER STILL SHOWS
 THIS PANEL "D" COMING FROM PANEL "M"?
 WAS IT DISCOVERED IN THE "DEMO WORK"
 THAT THIS PANEL IS FED FROM "M" AND
 REASON WHY IT IS STILL SHOWN FROM "M"?
  
 THE FIRST REVIEW WAS DONE IN JULY 05 AND
 THE AMOUNT OF TIME AND DEMO WORK SINCE
 SHOULD REVEALED THIS INFORMATION.
  
  
 12)NOTE: NOTE #12 NO?? COULD NOT LOCATE.
 **
 PLEASE SHOW ALL CONTINUOUS
 LOADS AND LARGEST MOTOR ARE TO BE SHOWN
 @125%
 215.3,230.42 ETC,
  
  
  
 ****************************************
 THE FOLLOWING COMMENT HAS TO DO WITH
 ELECTRICAL RISER DIAGRAM,ONE-LINE
 DIAGRAM AND PANEL SCHEDULES.
 ****************************************
  
 13)NOTE: NOTE #13 NO, MOST OF THESE
 ITEMS WERE CORRECTED HOWEVER PLEASE SEE
 TC SHOWN AS 70A AND 100A ON ONE-LINE AND
 RISER.
 PLEASE SEE A NEW PANEL BR1 IS SHOWNON
 ONE-LINE, RISER, PANEL "LL" AND NOTED IN
 NOTES, HOWEVER NO PANEL SCHEDULE,
 CIRCUITING SUBMITTED TO VERIFY.
 **
  
 PLEASE CORRELATE ALL PANELS ON
 ONELINE, RISER AND PANEL SCHEDULES
 SUBMITTED.
 PLEASE SEE THERE ARE TOO NUMEROUS ITEMS
 WHICH DO NOT MATCH UP WITH EACH OTHER.
 PLEASE SEE AMERAGES OF PANELS SHOWN
 DIFFERENTLY ON EACH, SEE SOME SHOWN AS
 225A AND 300A ETC.
 PLEASE SEE SOME PANELS BEING SHOWN BEING
 FED FROM"DPB", YET OTHER SHEETS SHOW
 THESE PANELS FROM "DPA" AND YET PANEL
 SCHEDULES FOR THESE SHOW SOMETHING
 ELSE?? PLEASE SEE "DPA" TO G,GA,B, 2BA
 AND RISER SHOWS FROM "DPB" ETC.
 PLEASE SEE SOME PANEL SHOWN AS ONE SIZE
 MLO, YET INDICATE ON PANEL SCHEULE SHOWS
 A DIFFERENT SIZE.?
 PLEASE SEE PANELS LABELED AS ONE THING
 ON ONE-LINE ANDSOEMTHING ELSE ON RISER
 DIAGRAM AND PANEL SCHEDULE? KDP, KDP1,
 600A/ 500A??? ETC,,
 PLEASE SEE POOL RM PANEL, PANEL N ETC.
 PLEASE SEE ONE LINE SHOWS DISCONNECT
 FROM WW MDP TO KDP/KDP1, YET RISER DOES
 NOT SHOW THIS?
 PLEASE SEE SOME PANELS SHOWN AS MLO, YET
 ALSO SHOWS HAVING A MAIN?
 PLEASE INCLUDE ALL INFORMATION FOR ALL
 DISCONNECTS ON RISER.
 PLEASE LABEL ALL PANELS,DISC'S, MDP ETC
 ON RISER.
  
 ********************************
 NEW NOTES DUE TO CHANGES AND INFORMATION
 BEING CHANGED AND/OR SUBMITTED.
  
 1)NOTE: PLEASE SEE ORIGINAL NOTES WITH
 RESPECT TO SHOWING ALL CIRCUITING,PLEASE
 SEE MOST CIRCUITING IS NOW SHOWN,
 HOWEVER PLEASE SEE SOME OF THE FOLLOWING
 WHICH DO NOT SEEM TO CORRELATE ETC.
  
 *PLEASE SEE CIRCUITING ON PANEL "N",
 MOST A/C EQUIPMENT IS NOTED AS BEING
 3-POLE ITEMS, HOWEVER CIRCUITING ON
 PANEL SCHEDULES, SHOWS ITEMS TAKING THE
 SPACE AND NUMBERED AS 2-POLE?
  
 *PLEASE SEEE-2.1A, SHOWS 86 AHU-9 TO
 DPB-1, YET DPB, IS BLANK AT THIS
 LOCATION.
  
 *PLEASE SEE E-2.1.C UNIT LABELED AS
 EDH-1, PANEL "N", YET PANEL "N" DOES NOT
 SHOW THIS. ALTHOUGH, THERE SEEMS TO BE A
 UNIT WHICH HAS THE SAME KW RATING ETC,
 HOWEVER IT IS LABELED"DEH", IS THIS
 THE SAME AND ONLY A MISPRINT?
  
 *PLEASE SEE E-2.1.C WHICH SHOWS 5AHU-7
 TO "N", YET THIS COULD NOT BE LOCATED ON
 "N"?
  
 *PLEASE SEE E-2.2A, 86AHU-5 TO D-7,9,11,
 NEW OR EXSITING. ?AS MANY NEW AREAS
 ARE NOW SHOWN SHADED, WHICH WERE NOT ON
 ORIGINAL PLANS?
  
 2)NOTE: PLEASE SEE NOTES ON PLANS
 CONTAIN NUMERICAL NOTES TO SEE 4.1 FOR
 PANELS ETC, HOWEVER THIS ROOMS SEEMS TO
 BE MISSING IDENTIFICATION ETC ETC.
  
 3)NOTE: PLEASE SEE PLANS NOW HAVE NOTES
 ADDED FOR SOME ITEMS. PLEASE KNOW, NOTES
 BEING ADDED TO PLANS DO NOT ALLEAVIATE
 THE DESIGN PROFESSIONAL FROM PROVIDING
 THE TECHNICAL INFORMATION NEEDED. PLEASE
 SEE NOTE WHICH MENTIONS TO SEE ARCHITECT
 TO DETERMINE HEIGHTS ETC. PLEASE KNOW,
 THESE THINGS SHOULD BE ON SAID PLANS.
  
 4)NOTE: PLEASE SEE PANEL DPB WHICH SHOWS
 THE DE-RATED LOAD FROM PANEL "N", WHICH
 SEEMS TO HAVE BEEN DER-RATED ONCE AGAIN
 FOR DPB CALCS???
 PLEASE CLARIFY THIS.
  
 5)NOTE: PLEASE SEE ATTACHED COPY OF FS
 553.80(2)(B) WITH RESPECT TO DESIGN
 PROFESSIONAL AND REPEAT COMMENTS.
 PLEASE KNOW, IF PLANS COME BACK WITH ANY
 OF THE SAME COMMENT SFROM THE FIRST
 REVIEWS NOT ADDRESSED FOR CODE
 COMPLIANCE, THE STATE STATUES, REQUIES A
 4X FEE BE ASSESSED FOR THE PLAN REVIEW
 PORTION OF THE BASE PERMIT FEE. (30% X4)
 TO THE DESIGN PROFESSIONAL FOR REPEAT
 COMMENTS.
 PLEASE KNOW, IT IS STRONGLY SUGGESTED A
 MEETING BE HELD TO GO OVER COMMENTS AS
 NOT TO HAVE THIS IMPLEMENTED.
 THIS AMOUNT WOULD COME TO $13,800.00.
 PLEASE KNOW THE 10% RE-SUB WILL BE DUE
 WHEN PLANS COME BACK IN FOR THIRD
 REVIEW.
 ** PLEASE KNOW, ONE COPY OF THIS
 SUBMITTIAL OF ELECTRICAL PLANS WILL BE
 RETAINED AND PLACED WITH PLANS FROM
 ORIGINAL REVIEW WHICH WERE ALSO
 REETAINED.
  
  
 ** PLEASE BE SURE TO SEE ANY COMMENTS
 FROM OTHER REVIEWER(S) WHICH MAY AFFECT
 ELECTRICAL PLANS.
  
 **PLEASE GO THROUGH ALL PLANS PANELS,
 DISCONNECTS ETC AND CORRELATE.
  
  
 PLEASE REMOVE ALL OLD/VOIDED SHEETS AND
 ONLY INSERT NEW REVISED SHEETS INTO
 COMPLETE SETS FOR REVIEW AND STAMPING.
 ONE SET OF OLD/VOIDED SHEETS FROM OTHER
 TRADES SHOULD BE SUBMITTED FOR
 REFERENCE. THIS WILL NOT BE REQUIRED OF
 VOIDED ELECTRICAL SHEETS AS ONE SET IS
 ALREADY RETAINED.
  
 PLEASE SUBMIT THE ABOVE INFORMATION FOR
 REVIEW. IF THERE ARE ANY QUESTIONS,
 PLEASE DO NOT HESITATE TO CALL.
  
 DEWEY PALMER
 ELECTRICAL PLAN REVIEW
 561-805-6717
 [email protected]
2005-12-27 00:00:00REVIEW WILL GO INTO "F" STATUS, REVIEW
 IN PROGRESS.
 NOTES TO FOLLOW.
2005-12-26 00:00:00ONE ROLL IN ELECTRICAL FOR REVIEW.
 NO RESPONSE LETTER(S) FROM DESIGN
 PROFESSIONALS SUBMITTED.