| 2005-09-09 00:00:00 | ******** UNSAT ********** |
| | |
| | PLEASE SEE SOME NOTES FROM PREVIOUS |
| | REVIEW AND SOME NEW NOTES. |
| | |
| | 1)NOTE: PLEASE SEE RANGE OCP HAS NOW |
| | BEEN CHANGED FROM 70A TO 55A'S. PLEASE |
| | SEE 240.6, 55A'S IS NOT A SIZE OCP |
| | AVAILABLE. |
| | |
| | 2)NOTE: PLEASE SEE "EQUIPMENT GROUNDING" |
| | CONDUCTOR IS STILL BEING SHOWN TO THE |
| | FIRST MEANS OF DISCONNECT. |
| | PLEASE SEE 250.6,250.24. THIS IS |
| | INDICATED AS "BOND" ON PLANS. |
| | ONLY THE UN-GROUNDED (HOT) , AND THE |
| | GROUNDED (NEUTRAL) CONDUCTORS ARE |
| | INSTALLED UP TO THE FIRST MEANS OF |
| | DISCONNECT. |
| | |
| | 3)NOTE: PLEASE SEE GROUNDING ELECTRODE |
| | SYSTEM SHALL BE COMPLETE AND CONTINUOUS |
| | AT ONE LOCATION. |
| | PLEASE SEE RISER SHOWS SOME FROM METER |
| | AND THEN , FOOTER AND COLD WATER AT MDP? |
| | PLEASE MOVE GROUNDING ELECTRODES (FOOTER |
| | STEEL AND COLD WATER ) OVER TO GRND RODS |
| | SHOWN AT METER. |
| | 250.50,250.58 |
| | |
| | 4)NOTE: PLEASE CORRELATE ALL A/C |
| | EQUIPMENT. PLEASE SEE RISER INDICATES |
| | 3-#6'S AND 3-#8'S FOR AHU'S AND CU'S |
| | ALONG WITH EQUIPMENT GROUNDING |
| | CONDUCTORS(BOND AS SHOWN). PLEASE SEE |
| | THE AMOUNT OF CONDUCTORS TEND TO |
| | INDICATE EQUIPMENT AS 3-PHASE. PLEASE |
| | SEE RISER/SERVICE AND PANELS INDICATE A |
| | SINLGE PHASE SERVICE. |
| | PLEASE ADJUST. |
| | PLEASE ALSO SEE PANEL SCHEDULE INDICATES |
| | ALL CONDUCTORS AS #6'S, AS #8'S ARE |
| | NOTED FOR RISER. |
| | PLEASE ADJUST. |
| | |
| | 5)NOTE: PLEASE SEE THE RECEPT WAS ADDED |
| | FOR WHIRLPOOL TUB, HOWEVER NO INDICATION |
| | OF REQUIRED GFI PROTECTION IS SHOWN? |
| | PLEASE SEE 680.71 |
| | |
| | 6)NOTE: PLEASE CLARIFY CONTINUOUS LOAD |
| | OF 125% IS ALREADY FIGURED FOR POOL |
| | PUMP? |
| | 215.3, 230.42 ETC. |
| | |
| | 7)NOTE: NEW. PLEASE SEE SD SHOWN FOR |
| | MASTER BEDRM WILL BE REQUIRED TO BE |
| | MOVED INTO BEDRM AREA WITHIN THE 12" OF |
| | HIGHEST CEILING POINT ON A FLAT CEILING. |
| | NFPA-72 11.8.3.5 |
| | PLEASE SEE A SD WILL BE REQUIRED INSIDE |
| | "STUDY" AS THIS IS CONSIDERED AN |
| | ADAPTABLE SLEEPING RM. |
| | NFPA-72 11.5.1.1 |
| | |
| | 8)NOTE: PLEASE CORRLEATE LOAD AND OCP |
| | FOR WATER HEATER. SHOWS 9KW FOR WH. |
| | PLEASE VERIFY THIS , AS 9KW SEEMS TO BE |
| | HIGH FOR A 60 GAL UNIT. PLEASE SEE MIN |
| | OCP FOR WH IS 125%. 422.13 MAX 150%. |
| | (IS THIS 4500 UPPER AND 4500 LOWER?) |
| | |
| | 9)NOTE: PLEASE SEE TWO GDO'S ARE SHOWN |
| | ON LOAD CALCS, HOWEVER ONY ONE IS |
| | INDICATED ON PANEL SCHEDULE. |
| | PLEASE SEE THREEDEDICATED REFRIGERATOR |
| | CIRCUITS ARE SHOWN ON PANEL SCHEDULE, |
| | HOWEVER ONLY TWO ARE IN LOAD CALCS. |
| | |
| | 10)NOTE: PLEASE SEE LT FIXTURE IN STUDY |
| | CLOSET WILL BE REQUIRED TO MEET 410.8 |
| | LT IS SHOWN OVER SHELF. |
| | |
| | NOTE TO FS 553.80(2)(B), ONLY A NOTICE. |
| | |
| | PLEASE REMOVE ALL OLD VOIDED SHEETS AND |
| | ONLY INSERT NEW SHEETS . (AS PREVIOUSLY |
| | DONE). |
| | |
| | PLEASE SUBMIT THE ABOVEINFORMATION AND |
| | IF THERE ARE ANY QUESTIONS, PLEASE CALL. |
| | |
| | DEWEY PALMER |
| | ELECTRICAL PLAN REVIEW. |
| | |
| | DEWEY PALMER |
| | ELECTRICAL PLAN REVIEW |
| | 561-805-6717 |
| | [email protected] |
| | |
| | PLEASE SUBMIT THE ABOVE INFORMATION FOR |
| | REVIEW. |