| 2005-08-01 00:00:00 | DENIED; |
| | 1.POOL COMPLIES WITH FBC-2001 SEC 424.2 |
| | PRIVATE SWIMMING POOLS (ADD TO NOTES) |
| | 2.SEC. 424.2.6/1 ENGINEERING DESIGN, |
| | CONSTRUCTION AND WORKMANSHIP PER. |
| | ANSI/NSPI-5 (ADD TO NOTES) |
| | 3.SEC.424.2.6.6.2 SHOW COMPLIANCE WITH |
| | ANSI/ASME A112.19.8M. PROVIDE MODEL |
| | NUMBER AND MANUF. INFORMATION FOR |
| | VAC.LOCK. (GIVE DETAIL , SUBMITTLE OR |
| | ADD TO NOTES) |
| | 4.SEC.424.2.8/1 -4 VALVES SHALL BE |
| | APPROVED BY FBC-2001.THEY WILL BE |
| | READILY ACCESSIBLE FOR MAINT. AND |
| | REMOVAL. FULL WAY VALVES SHALL BE |
| | INSTALLED. WHERE CHECK VALVES ARE |
| | INSTALLED THEY SHALL OF THE SWING OR |
| | VERTICAL CHECK PATTERNS. |
| | 5.SEC.424.2.9 WATER SUPPLY, LOCAL ORD. |
| | #2853-95, BACKFLOW REQUIRED ON WATER |
| | SERVICE. (ADD TO NOTES) |
| | 6.SEC.424.2.12.1PRESSURE TESTS. PER. |
| | MANUFACTURE RECOMMENDATIONS, NO AIR TEST |
| | SHALL BE APPROVED FOR PVC PIPE AND |
| | FITTINGS. (ADD TO NOTES) |
| | 7.SEC.424.2.13.2 JOINTS AND CONNECTIONS. |
| | FBC PLUMBING SEC. 605.21, PURPLE PRIMER |
| | REQUIRED ON PVC PIPE. (ADD TO NOTES) |
| | 8.SEC.424.2.15 GAS PIPING SHALL COMPLY |
| | WITH FBC 2001 FUEL GAS. SEPARATE PLANS |
| | AND PERMIT REQUIRED. |
| | PLUMBING PLAN REVIEW BY; |
| | JOHN LEECH |
| | 805-6695 |