| Date |
Text |
| 2005-12-20 00:00:00 | ****** UNSAT ***** |
| | |
| | PLEASE SEE MINOR CHANGES NOTED ON |
| | REVISION COVER SHEET, HOWEVER THERE AHVE |
| | BEEN SOME MAJOR CHNAGES NOT ON ORIGINAL |
| | PLANS. |
| | |
| | |
| | 1)NOTE: PLEASE SEE MANY WINDOWS ADDED |
| | NOT ON PREVIOUS ELECTRICAL PLANS. |
| | PLEASE SEE 210.62, 220.12A FOR MIN "SHOW |
| | WINDOWS" NOW REQUIRED ABOVE ALL WINDOWS. |
| | PLEASE ALSO ADJUST ALL CIRCUITING FOR |
| | THESE AS THEY ARE REQUIRED TO BE ON |
| | SEPARATE CIRCUITS. |
| | |
| | 2)NOTE: PLEASE SEE A PANEL "E" IS SHOWN |
| | ON ON MDP , HOWEVER NO PANEL "E" |
| | SCHEDULE WAS SUBMITTED. IS THIS "EM" ON |
| | PLANS? |
| | PLEASE CORRELATE. |
| | |
| | 3)NOTE: PLEASE SEE MDP IS NOW SHOWN AS |
| | MLO ON SCHEDULE AND MCB ON RISER. PLEASE |
| | SEE 230.70,230.71 ETC, A MAIN CIRCUIT |
| | BREAKER WILL BE REQUIRED. |
| | PLEASE MAKE NESS CHANGES. |
| | PLEASE ALSO SEE MDP SEEMS TO INDICATE A |
| | "SPARE" 800A 3-P IN SPACE #7?? PLEASE |
| | VERIFY. |
| | |
| | 4)NOTE: PLEASE KNOW, DUE TO THE SCOPE OF |
| | WORK BEING DONE AND THE REQUIREMENTS OF |
| | CHAPTER 34 OF THE FBC, ALL EXISTING AND |
| | NEW ELECTRICAL SHALL MEET CURRENT 2002 |
| | NEC. |
| | PLEASE SEE ALL OCP SHOWN AS EXISITNG FOR |
| | EQUIPMENT, A/C 'S ETC. THESE SHOULD BE |
| | VERIFIED IN FEILD AND ADJUSTED IF OCP |
| | DOES NOT MEET MIN OR IS SIZED TOO HIGH |
| | FOR UNIT. |
| | |
| | |
| | ** PLEASE SEE ANY POSSIBLE COMMENTS FROM |
| | OTHER REVIEWERS WHICH MAY AFFECT |
| | ELECTRICAL PLANS. |
| | |
| | PLEASE SUBMIT THE ABOVE INFORMATION FOR |
| | REVIEW. IF THERE ARE ANY QUESTIONS, |
| | PLEASE DO NOT HESITATE IN CONTACTING |
| | THIS OFFICE. |
| | |
| | DEWEY PALMER |
| | ELECTRICAL PLAN REVIEW |
| | 561-805-6717 |
| | [email protected] |