| 2006-10-28 07:06:30 | PAUL SCHMITZ, PLUMBING & GAS PLANS |
| | EXAMINER561-805-6692 |
| | |
| | [email protected] |
| | PLUMBING GAS PLAN REVIEW FBC 2001 |
| | |
| | DENIED |
| | |
| | PREVIOUS NOTES FOR GAS NOT ADDRESSED |
| | |
| | WHEN RESUBMITTING. |
| | PLEASE INCLUDE A RESPONCE LETTER INDICATING HOW THE |
| | ITEMS WERE ADDRESSED, THIS WILL HELP TO EXPIDITE THE |
| | PLAN REVIEW. |
| | |
| | (1) SHT 2, GAS SYSTEM IS REQUIRED TO HAVE A EMERGENCY |
| | SHUT OFF VALVE FOR COOKING |
| | EQUIPMENT. A SHUTOFF VALVE IS REQUIRED UP STREAM STREAM |
| | OF THE EMERGENCY VALVE |
| | AND A UNION DOWN STREAM, SO VALVE CAN BE REPLACED OR |
| | REPAIRED. |
| | |
| | (2)SHT 2, PROVIDE A GAS PIPING ISOMETRICSUBMIT AN |
| | ISOMETRIC DRAWING THAT CLEARLY SHOWS ALL CUT SECTIONS |
| | OF PIPE |
| | AND CORRESPONDING LENGTHS PER FBC-2001 FUEL GAS CODE. |
| | |
| | (3) SHT 2,SHOW TYPE OF PIPING MATERIAL BEING |
| | INSTALLED, ALL PIPE SIZES, (AND THE EDH NUMBER OF |
| | CORRUGATED STAINLESS STEEL |
| | TUBING FOR EACH PIPE SIZE BEING USED. |
| | |
| | (4) SHT 2, TYPE OF GAS, (LP OR NATURAL) |
| | |
| | (5) SHT 2, BTU LOAD OF EACH APPLIANCE AND THE TOTAL BTU |
| | LOAD ON THE SYSTEM. REFER TO THE FBC-2001 FUEL GAS CODE |
| | SECS. 401.8 |
| | THRU 402.5.2 AND TABLES 402(1) THRU 402(34). |
| | |
| | (6) SHT 2,SHOW THE DISTANCE FROM THE POINT OF |
| | DELIVERY, (METER), TO THE MOST REMOTE OUTLET IN THE |
| | BUILDING AND/OR SYSTEM PER |
| | FBC-2001 FUEL GAS CODE APPENDIX A - USE |
| | OF CAPACITY TABLES (A)(3). |
| | |
| | (7) SHT 2,INDICATE THE DELIVERY PRESSURE (PSI) PER |
| | FBC-2001 FUEL GAS CODE SEC. 402.2. NATURAL GAS SPECIFY |
| | .5 PSI OR 2 PSI. |
| | |
| | (8) SHT 2, SUBMIT MANUFACTURE SHEETS FOR ALL GAS |
| | EQUIPMENT TO VERIFY COMPLIANCE WITH STANDARDS NFPA 54, |
| | NFPA 58, AND THE |
| | FBC-2001 FUEL GAS CODE SEC 402.2 |
| | |
| | END OF COMMENTS |