| 2005-03-07 00:00:00 | DENIED |
| | |
| | 1) SUBMIT COMPLETE STATE PRODUCT |
| | APPROVAL WITH TEST REPORTS, LIMITATIONS |
| | AND INSTALLATION INSTRUCTIONS AND |
| | DRAWINGS FOR THE ASPHALT SHINGLES. MEAN |
| | ROOF HEIGHT IS LESS THAN 33 FEET, |
| | THEREFORE, MIAMI-DADE NOA IS ACCEPTABLE. |
| | |
| | 2) ASTM C 926 REQUIRES PORTLAND CEMENT |
| | PLASTER TO BE 5/8" THICK WHEN APPLIED |
| | HORIZONTALLY OVER METAL PLASTER BASE. |
| | PLEASE REVISE THE SOFFIT DETAILS ON A-2. |
| | |
| | 3) THE CITY OF WPB AMENDMENTS TO FBC |
| | TABLE 2306.1 REQUIRES THE ROOF SHEATHING |
| | TO BE NAILED AT 4" O.C. AT THE EDGES AND |
| | 6"O.C. INTERMEDIATE IN ZONE 3, WHICH IS |
| | THE OUTSIDE CORNERS ON HIP ROOFS. |
| | |
| | 4) THE UPLIFTS AND GRAVITY LOADS |
| | SPECIFIED ON S1 FOR TRUSSES S2 AND HGS |
| | ARE LESS THAN THOSE LISTED ON THE TRUSS |
| | DRAWINGS. PLEASE CORRECT. |
| | |
| | 5) SUBMIT SITE PLANS INDICATING THE |
| | LOCATION OF THE STRUCTURE. |
| | |
| | 6) FBC 11-4.2.6 REQUIRES THE SIDE REACH |
| | OF A PERSON IN A WHEEL CHAIR USING A |
| | PARALLEL APPROACH TO BE 54" FOR THE |
| | MAXIMUM HIGH SIDE REACH AND THE LOW SIDE |
| | REACH SHALL BE NO LESS THAN 9" ABOVE THE |
| | FLOOR. SHOW COMPLIANCE OF MAIL BOX |
| | UNITS. |
| | |
| | ROBERT MCDOUGAL |
| | BLDG. PLAN REVIEW |
| | (561)805-6714 |
| | |