| Date |
Text |
| 2005-07-21 00:00:00 | ****CORRECTIONS**** |
| | |
| | SAMANTHA HILL, BUILDING PLANS EXAMINER |
| | 561-805-6724 [email protected] |
| | |
| | FBC FLORIDA BUILDING CODE 2001 |
| | FBC* CITY OF WEST PALM BEACH AMENDMENTS |
| | TO THE FBC2001 |
| | |
| | THE FOLLOWING COMMENTS ARE FROM THE |
| | PREVIOUS REVIEW. |
| | |
| | 1.)SEE PROPERTY APPRAISER VALUATION |
| | ATTACHED.THIS IS AN OVER 50% |
| | IMPROVEMENT AND MUST COMPLY WITH |
| | FBC3401.7.2.6.THIS SECTION AFFECTS |
| | OTHER COMMENTS ON THIS LIST. (WAS |
| | ACKNOWLEDGED.) |
| | |
| | 2.)PROVIDE A COPY OF THE SURVEY FOR |
| | THIS PROPERTY. |
| | |
| | THE SURVEY SHOWS A 1 STORY GARAGE ON THE |
| | PROPERTY LINE.PROVIDE INFORMATION IN |
| | REGARDS TO THIS BUILDING AND SHOW FBC |
| | TABLE 600 COMPLIANCE. |
| | |
| | 3.)THIS APPEARS TO BE TWO UNITS; ONE |
| | UPSTAIRS, ONE DOWNSTAIRS.2ND FLOOR IS |
| | TO BE IMPACT GLASS, CITY OF WEST PALM |
| | BEACH IMPLEMENTATION STANDARD FOR |
| | HURRICANE MISSILE IMPACT PROTECTION, |
| | ITEM #13, SEE ATTACHED.SUBMIT A |
| | HURRICANE INSTALLATION PLAN INCLUDING |
| | WHERE THE SHUTTERS WILL BE STORED FOR |
| | SHUTTERS USED ON THE FIRST FLOOR. |
| | |
| | THIS WAS ADDRESSED BY CHANGING THE |
| | SECOND FLOOR TO IMPACT AND A NOTE |
| | STATING THAT THE FIRST FLOOR SHUTTERS |
| | WOULD BE STORED IN THE UTILITY ROOM |
| | BELOW THE STAIRS.ONLY THE BUILDING |
| | OFFICIAL CAN APPROVE THE USE OF SHUTTERS |
| | ON A COMMERCIAL BUILDING.PLEASE SUBMIT |
| | A HURRICANE SHUTTER INSTALLATION PLAN |
| | FOR REVIEW.THIS IS TO INCLUDE ALL |
| | PERTINENT INFORMATION SUCH AS STORAGE |
| | LOCATION, SIZE OF STORAGE AREA, WHERE |
| | THEY ARE STORED IN THAT AREA, HOW THEY |
| | ARE SECURED IN THAT LOCATION; WHO IS TO |
| | INSTALL THEM; TIME ESTIMATE FOR |
| | INSTALLATION; WHEN THE SHUTTERS WILL BE |
| | INSTALLED, ETC.THIS MAY BE SUBMITTED |
| | SEPARATELY FROM PLAN REVIEW (NO FEE). |
| | |
| | 4.)THE BALCONY (MEANS OF EGRESS FOR |
| | 2ND FLOOR UNIT) IS TO COMPLY WITH |
| | FBC1014.1.SHOW FIRE RESISTANCE (UL |
| | ASSEMBLY OR CALCULATED FBC CHAPTER 7), |
| | PROVIDE DOOR FIRE RATING INFORMATION. |
| | |
| | THE FIRE RATING FOR THE DOOR WAS |
| | PROVIDED.I BELIEVE THAT THIS WAS |
| | ADDRESSED BY SHOWING TWO LAYERS OF |
| | DRYWALL ON THE CEILING OF THE FIRST |
| | FLOOR UNIT.PROVIDE CALCULATED FIRE |
| | RESISTANCE FOR THE FLOOR/CEILING |
| | ASSEMBLY FBC709 (EACH COMPONENT AND |
| | TIME, SHOW TOTAL). |
| | |
| | 5.)THE EXTERIOR STAIR IS TO COMPLY |
| | WITH FBC1006.2.4.SHOW FIRE RESISTANCE |
| | OF THE WALL.OPENINGS WITHIN 10' ARE |
| | TO BE 3/4 HR.INDICATE ON THE PLAN. |
| | |
| | FIRE RESISTANCE OF THE WALL REQUIRED BY |
| | FBC1006.2.4 WAS NOT SHOWN.THERE IS A |
| | NOTE ON THE PLAN REGARDING OPENINGS.IT |
| | IS THE RESPONSIBILITY OF THE DESIGNER TO |
| | DETERMINE WHICH OPENINGS ARE TO BE |
| | PROTECTED.INDICATE ON THE ELEVATIONS, |
| | FLOOR PLAN OR A SCHEDULE. ALSO INCLUDE |
| | THE REAR BUILDING.SHOW RATED WALL |
| | REQUIREMENT ON THE FLOOR PLAN AS WELL AS |
| | A DETAIL SHOWING HOW IT COMPLIES. |
| | |
| | 6.)THIS PROPERTY IS ON THE DEMO LIST. |
| | AN ORDER FROM THE BOARD FOR REPAIRS |
| | MUST BE GRANTED BEFORE A PERMIT CAN BE |
| | ISSUED. |
| | |
| | AN ORDER WAS GRANTED, BUT IT IS MY |
| | UNDERSTANDING THAT ALL BUILDINGS ARE TO |
| | BE BROUGHT TO 100% CODE COMPLIANCE.THE |
| | REAR BUILDING AND GARAGE ARE ALSO TO BE |
| | INCLUDED IN THIS PERMIT, ALTHOUGH A |
| | SEPARATE PERMIT NUMBERS AND APPLICATION |
| | FORMS WILL BE REQUIRED.PLEASE CONTACT |
| | ME IF YOU FEEL THAT MY UNDERSTANDING IS |
| | NOT CORRECT. |
| | |
| | 7.)SHEATHING NAILING IS TO COMPLY |
| | WITH CITY OF WEST PALM BEACH AMENDMENTS |
| | TO THE FBC TABLE 2306.1.SEE ATTACHED. |
| | |
| | NOT ADDRESSED.FBC*TABLE 2306.1.NON |
| | COMPLIANT FOR ZONE 3 (4/6, NOT 6/6). |
| | |
| | 8.)PROVIDE DESIGN PRESSURES FOR THE |
| | ROOF. |
| | |
| | PLEASE CLARIFY HOW YOU HAVE DETERMINED |
| | THE PRESSURE TO BE +-38.87, FBC1606.2B. |
| | SHOULDN?T THIS BE -89? |
| | |
| | 9.)FOR THE MODIFIED ROOF, INDICATE |
| | WHICH METHOD OF INSTALLATION YOU ARE |
| | USING. |
| | |
| | THIS SHOULD BE DONE BY CHOOSING ONE OF |
| | THE APPROVED ASSEMBLIES ON THE PRODUCT |
| | APPROVAL. |
| | |
| | 10.)SPECIFY THE STRAPS.FASTENING |
| | MUST BE CONSISTENT WITH THE |
| | MANUFACTURER'S SPECIFICATIONS. |
| | |
| | SOME STRAPS WERE SPECIFIED, OTHERS HAD |
| | ONLY A SIZE.THIS IS A STRUCTURAL |
| | COMPONENT REQUIRING TESTING OR |
| | ENGINEERING AND STATE OR LOCAL PRODUCT |
| | APPROVAL FAC9B72.SPECIFY STRAP, |
| | MANUFACTURER AND NUMBER, AND FASTENING |
| | IN ACCORDANCE WITH MANUFACTURER |
| | INSTRUCTIONS. |
| | |
| | NEW COMMENTS |
| | |
| | 11.)BATHROOM DOOR ON THE FIRST FLOOR |
| | IS TO COMPLY WITH FBC11-11(1), CLEAR |
| | OPENING OF AT LEAST 29IN. |
| | |
| | 12.)THE ELEVATIONS AND WALL SECTION DO |
| | NOT MATCH.IS THERE A PARAPET WALL?IF |
| | THERE IS, SHOW DRAINAGE FBC1503.4. |
| | |
| | 13.)THREE DIFFERENT NOAS ARE INCLUDED |
| | IN THE DOOR PRODUCT APPROVAL PACKAGE |
| | SUBMITTED.PLEASE SUBMIT ONLY THE DOOR |
| | YOU ARE USING. |
| | |
| | 14.)PROVIDE ENERGY CALCS FOR THE REAR |
| | BUILDING. |
| | |