| 2004-12-13 00:00:00 | ****CORRECTIONS**** |
| | |
| | SAMANTHA HILL, BUILDING PLANS EXAMINER |
| | [email protected] |
| | |
| | 1.)THE WINDOWS ON THE SECOND FLOOR |
| | MUST BE IMPACT GLASS.PLEASE NOTE THAT |
| | THE PRODUCT APPROVAL SUBMITTED IS FOR A |
| | FIXED WINDOW, PLAN SHOWS OPERABLE |
| | (CASEMENT) |
| | |
| | 2.)REGARDING THE INSTALLATION PLAN |
| | FOR |
| | HURRICANE PROTECTION, PLEASE SUBMIT AN |
| | ORIGINAL CONTRACT WITH KLEAN K. |
| | SERVICES.SERVICES ARE TO BE PERFORMED |
| | BY INDIVIDUALS WITHIN PALM BEACH COUNTY |
| | AS PER THE POLICY; PLEASE NOTE IN THE |
| | PROPOSED PLAN. |
| | |
| | 3.)SEE THE SOILS REPORT; CONTINUOUS |
| | FOOTINGS ARE TO BE MIN 18" BELOW GRADE. |
| | F1 APPEARS TO BE BETWEEN 12-14" BELOW |
| | GRADE.ALSO SEE 6.3.2 OF THE ORIGINAL |
| | SOILS REPORT; WAS DESIGNER OF RECORD |
| | AWARE OF THE RECOMMENDATION IN REGARDS |
| | TO MONOLITHIC SLABS?PLEASE ASK DOR TO |
| | READ BOTH SOILS REPORTS BEFORE |
| | RESUBMITTAL. |
| | |
| | 4.)SOILS REPORTS ARE TO BE SEALED. |
| | |
| | 5.)SEE THE PREVIOUS LIST, ITEM #11. |
| | RECEIPT OF AN UNSEALED LETTER |
| | ADDRESSING |
| | THIS MATTER FROM SHAWN STAMBAUGH, PE IS |
| | ACKNOWLEDGED.IF THE FASTENING |
| | CONFLICTS WITH THE TECHNICAL BULLETIN |
| | FROM |
| | THE MANUFACTURER, LOCAL PRODUCT |
| | APPROVAL |
| | (WITH CALCULATIONS) IS REQUIRED |
| | FAC9B-72.PLEASE FEEL FREE TO CONTACT |
| | ME TO DISCUSS. |