| Date |
Text |
| 2004-10-14 00:00:00 | DENIED |
| | REFERENCE: FBC-2001 PLUMBING |
| | FBC-2001 CHAPTER 1 |
| | FBC-2001 CHAPTER 11 |
| | FBC-2001 BUILDING |
| | NFPA-99C MED-GAS |
| | |
| | FROM PREVIOUS REVIEW: COMMENT NUMBER TO |
| | REMAIN THE SAME TO AVOID CONFUSION. |
| | 3) SHT A.1 SHOW CLEAR FLOOR SPACE REQUI- |
| | RED BY SECTION 11-4.24.5 WHICH SHALL BE |
| | PROVIDED IN FRONT OF THE SINKS TO ALLOW |
| | FORWARD APPROACH. THIS IS FOR THE SINKS |
| | IN THE COFFEE ROOM AND THE CONFERENCE |
| | ROOM. SINKS SHALL COMPLY WITH SECTION |
| | 11-4.24 AND ALL SUBSECTIONS. DETAIL DOES |
| | NOT SHOW HEIGHT 11-4.24.2, KNEE CLEARAN- |
| | CE 11-4.24.3, SINK DEPTH 11-4.24.4, |
| | CLEAR FLOOR SPACE 11-4.24.5, (ONLY THE |
| | TURNING AREA IS SHOWN), SEE FIG. 32, |
| | EXPOSED PIPES AND SURFACES 11-4.24.6. |
| | 6) SHT P-1 X-RAY PROCESSOR, SUBMIT MAN- |
| | UFACTURE SPECIFICATION/INSTALLATION |
| | SHEETS. THIS PROCESSOR MAY REQUIRE A |
| | CHEMICAL NUTRALIZER AND/OR A METAL INT- |
| | ERCEPTOR. IF EITHER IS REQUIRED, RODNEY |
| | COMPO, ENVIRONMENTAL COMPLIANCE SHALL BE |
| | CONTACTED. WASTE ORD. #2938-96. TO CON- |
| | TACT MR. COMPO (561) 837-4074. - NO RES- |
| | PONSE NOTED TO THIS COMMENT. |
| | 7) SHT P.1 UNDER COUNTER WATER HEATER |
| | SHALL BE ACCESSIBLE. PLEASE SUBMIT A DE- |
| | TAIOL. SECTION 501.4. - NO RESPONSE NOT- |
| | ED. |
| | 8) SHT P.1 INDICATE TYPE OF SINK LOCATED |
| | IN THE CLOSET WITH THE VACUUM AND THE |
| | AIR COMPRESSOR. SECTION 104.2.1 - NO RE- |
| | SPONSE NOTED TO THIS COMMENT. |
| | 11) SHT P.4 WATER RISER DIAGRAM, AIR |
| | CHAMBERS ARE NOT APPROVED. DELETE FROM |
| | RISER DIAGRAM. SECTION 604.9 - WATER |
| | HAMMER ARRESTORS REQUIRED BY SECTION |
| | 604.9, (AT ICE MAKERS, DISH WASHERS, & |
| | WASH MACHINES), SHALL BE LOCATED NEAR |
| | THE FIXTURES IN AN "EFFECTIVE RANGE" NOT |
| | IN THE CEILING AS SHOWN. PDI-WH 201 AND |
| | MANUF. INSTALLATION INSTRUCTIONS. - SHOW |
| | WATER HAMMER ARRESTORS ON RISER DIAGRAM |
| | WHERE REQUIRED. |
| | 12) SHT WATER FILTER SHALL COMPLY WITH |
| | NSF-42, OR NSF-58 WHICH EVER APPLIES. |
| | SECTION 611.1 THRU 611.4. SUBMIT MANUF. |
| | SPECIFICATIONS. - NOT SUBMITTED. |
| | 13) BACKFLOW REQUIRED AT X-RAY PROCESSOR |
| | PER SECTION 608.16.9 - THIS IS SHOWN ON |
| | THE ICE MAKER AND NOT ON THE X-RAY PRO- |
| | CESSOR. |
| | 15) SHT P.5 COMPRESSOR DETAIL NOW CALLS |
| | FOR A 4" METAL VENT PIPE SHOWN ON SHEET |
| | AC-1. INDICATE THE TERMINATION POINT FOR |
| | THIS VENT PIPE. PROVIDE A DETAIL FOR THE |
| | TRANSITION FROM 2" PVC TO 4" METAL DUCT. |
| | SPECIFY MATERIAL OF METAL DUCT. T-FIN |
| | NOT APPROVED FOR THIS APPLICATION. |
| | 16) SHT P.5 VACUUM DETAIL NOT APPROVED. |
| | SEE SECTION 4-5.2.1.3 LIQUIDS FROM A |
| | LEVEL 3 VACUUM SYSTEM PER 4-5.2.2 SHALL |
| | BE DIRECTLY CONNECTED TO THE SANITARY |
| | DRAINAGE SYSTEM THROUGH AN APPROIATELY |
| | TRAPPED AND VENTED DRAIN. SEE ATTACHED |
| | SHEETS FROM FIRST REVIEW. |
| | ------------SECOND NOTICE-------------- |
| | *********WHEN RESUBMITTING PLANS******** |
| | PLEASE CLEARLY INDICATE THE REVISION AND |
| | REMOVE AND REPLACE ANY PAGES AS NECESS- |
| | ARY. SUBMIT (1) SET OF OLD DRAWINGS WITH |
| | THE PLANS WHEN RESUBMITTING PLANS. A |
| | TRANSMITTAL LETTER LISTING THE ORIGINAL |
| | REVIEW NUMBER, WITH A DESCRIPTION OF THE |
| | REVISION MADE, IDENTIFYING THE SHEET OR |
| | SPECIFICATION PAGE WHERE THE CHANGES CAN |
| | BE FOUND, WILL HELP TO EXPEDITE YOUR |
| | PERMIT. THANK YOU FOR YOUR ANTICIPATED |
| | COOPERATION. |
| | |
| | REVIEW BY KEN STEVENS |
| | (561) 805-6721 |
| | FAX (561) 653-2692 |
| | E-MAIL [email protected] |