| 2005-12-30 00:00:00 | ********** UNSAT ********** |
| | |
| | 1)NOTE: PLEASE SEE PREVIOUS NOTES DATED |
| | 11/21/05, 10/04 ETC. |
| | GENERATOR WAS TO DONE UNDER A SEPARATE |
| | PERMIT. THIS NOTICE TO BLDG CONTRACTOR |
| | WAS REDLINED ON PLANS IN 10/04", AND A |
| | PERMIT APPLICATION FOR GENERATOR WAS NOT |
| | MADE UNTIL 11//05. |
| | IT IS THE UNDERSTANDING OF THIS OFFICE |
| | THAT THE GENERATOR IS ALREADY INSTALLED |
| | AND WIRED INTO SERVICE. PLEASE SEE FBC |
| | 104AND FS 468 WHICH STATES WORK SHALL |
| | NOT COMMENCE WITH OUT THE POSTING OF |
| | SAID PERMIT FOR THE SCOPE OF WORK TO BE |
| | PERFORMED. |
| | PLEASE SEE A POSSIBLE 4X FEE MAY BE |
| | ADDED TO SAID GEN PERMIT BY INSPECTOR OR |
| | ELECTRICAL PLAN REVIEW FOR GEN. |
| | |
| | |
| | 2)NOTE: PLEASE SEE PREVIOUS REVIEW WHICH |
| | REQUIRES ALL EQUIPMENT/HEAT LOADS FOR |
| | AHU SHALL BE FIGURED AT 100%.THIS IS |
| | DONE.PLEASE KNOW, IT IS POSSIBLE TO SHED |
| | THE HEAT LOAD, HOWEVER A DETAIL ON |
| | METHOD AND WIRING OF THIS WAS REQUIRED |
| | TO BE PLACED ON PLANS, WHICH IS NOT. |
| | 702.5, 220,215.5 |
| | *** PLEASE ALSO SEE GEN SPECS FOR MAX |
| | LOADING, AS LOAD AT PRESENT IS 12.91 KW |
| | ON A 13KW GEN. THIS CURRENTLY MAY EXCEED |
| | THE 80% RECOMMENDED BY MANUFACTURE. |
| | PLEASE SEE SPECS FOR MAX CONTINUOUS LOAD |
| | FOR NAT GAS AND FOR LP. |
| | |
| | 3)NOTE: PLEASE SEE ORIG PLANS DID NOT |
| | SHOW THE LOCATION OF THE DISCONNECTING |
| | MEANS FOR GENERATOR. PLEASE SEE 230.72 |
| | AND 225.34 WHICH REQUIRES ALL MAINS TO |
| | BE GROUPED. PLEASE SEE A MCB IN THE GEN |
| | PANEL WOULD MEET THIS REQUIREMENT. |
| | PLEASE ADJUST PLANS AND REVISE. |
| | |
| | |
| | ** PLEASE SUBMIT THE ABOVE FOR REVIEW. |
| | IF THERE ARE ANY QUESTIONS, PLEASE CALL. |
| | |
| | DEWEY PALMER |
| | ELECTRICAL PLAN REVIEW |
| | 561-805-6717 |
| | [email protected] |