| 2005-04-06 00:00:00 | ****CORRECTIONS**** |
| | VARIOUS DETAILS PREPARED BY BIJAN |
| | PARSSI, PE |
| | |
| | SAMANTHA HILL, BUILDING PLANS EXAMINER |
| | [email protected] |
| | |
| | 1.)THE FORMER ARCHITECT AND ENGINEER |
| | HAVE SUBMITTED LETTERS STATED THAT THEY |
| | ARE NO LONGER DOR/EOR OF THE PROJECT. |
| | JIM PAINE, ARCHITECT, HAS SUBMITTED NEW |
| | PLANS.IS BIJAN PARSSI, PE THE NEW EOR |
| | FOR THIS PROJECT?OR IS THIS DELEGATED |
| | ENGINEERING?IF THIS IS DELEGATED |
| | ENGINEERING, THE DETAILS ARE TO BE |
| | REVIEWED BY DOR.IF HE IS THE NEW EOR, |
| | SUBMIT A LETTER STATING THIS AS ALL |
| | STRUCTURALS TO DATE HAVE BEEN SUBMITTED |
| | BY JIM PAINE. |
| | |
| | 2.)THE COLUMN CONNECTION PLAN IS NOT |
| | SEALED. |
| | |
| | 3.)AS PER CONVERSATION WITH THE |
| | CONTRACTOR, THE COLUMN CONNECTION PLAN |
| | IS SHOWING A C CHANNEL AND A STEEL |
| | COLUMN.THE DIMENSION 4X4X4 IS |
| | CONFUSING, IMPLIES A HEIGHT OF 4" RATHER |
| | THAN A COLUMN THE FULL HEIGHT.THE C |
| | CHANNEL IS SHOWN GRAPHICALLY BUT NOT |
| | SPECIFIED, WHAT SIZE?THE ANCHORING OF |
| | THE STEEL COLUMN AND C CHANNEL IS NOT |
| | SPECIFIED.ANCHORING AT THE BOTTOM OF |
| | THE COLUMN IS SPECIFIED, ASSUMING TO |
| | EXISTING SLAB ON 1ST FLOOR AS A CONCRETE |
| | ANCHOR IS SPECIFIED.IS THERE A BASE |
| | PLATE FOR THE COLUMN?SPECIFY WHERE |
| | THIS DETAIL IS TO BE USED. |
| | |
| | |