Plan Review Notes
Plan Review Notes For Permit 04051071
Permit Number 04051071
Review Stop E
Sequence Number 1
Notes
Date Text
2004-06-03 00:00:00********** UNSAT *******************
  
 PLEASE SEE THE FOLLOWING COMMENTS WHICH
 NOW AFFECT THE PERMITTING FOR THIS
 PROJECT SINCE ORIG ISSUED.
  
 1)NOTE: PLEASE SEE THE STATE HAS NOW
 ADOPTED THE 2002 NEC.
 PLANS WOULD NOW BE REQUIRED TO BE
 REVISED ACCORDING TO NEW NEC AND SUBMIT-
 -TED FOR REVIEW.
  
 2)NOTE: PLEASE SEE THE ENGINEER AS
 SHOWN ON ORIGINAL PLANS HAS BEEN TURNED
 IN TO FBPE'S FOR VIOLATIONS UNDER
 FS'S.
 PLEASE SEE FS 471.023, FS 471.025
 PLEASE ALSO SEE FAC 61G15-23.002.
  
 WE ARE UNABLE TO ISSUE A PERMIT AT THIS
 TIME PER THE ABOVE.
 PLEASE HAVE CORRECTIONS MADE.
  
 PLEASE ALSO SEE WE ARE NOW UNDER THE
 2001 FBC.
  
 PLEASE SUBMIT THE ABOVE INFORMATION FOR
 REVIEW. IF THERE ARE ANY QUESTIONS,
 PLEASE DO NOT HESITATE TO CALL.
  
 DEWEY PALMER
 ELECTRICAL PLAN REVIEW
 CITY OF WEST PALM BEACH
 CONSTUCTION SERVICES DEPT.
 561-805-6717
 [email protected]