| 2004-06-02 00:00:00 | BUILDING PLAN REVIEW: FAILED |
| | |
| | 1. BEFORE A PERMIT TO CONSTRUCT MAY BE |
| | ISSUED, IMPACT FEES MUST BE PAID TO |
| | PALMBEACH COUNTY.THE ACTUAL PERMIT |
| | PLANS |
| | MUST BE STAMPED BY THAT OFFICE, AND A |
| | COPY OF THE PAID RECEIPT ATTACHED TO |
| | THE PERMIT APPLICATION.PLEASE CALL |
| | (561) 233-5025 FOR MORE INFORMATION. |
| | |
| | 2. A NOTICE OF COMMENCEMENT MUST BE |
| | FILED WITH THE COUNTY CLERLS OFFICE AND |
| | A COPY SUBMITTED TO THE CITYBEFORE A |
| | PERMIT CAN BE ISSUED. |
| | |
| | 3. SHOW THE DESIGN PRESSURES OF ALL |
| | OPENINGS ON THE PLANS. NOTE: THE GARAGE |
| | DOOR PRODUCT APPROVAL SHOWS A DIFFERENT |
| | DESIGN PRESSURE THAN IS SHOWN ON THE |
| | PLANS. |
| | |
| | 4. THE W110 BUTT GLASS ASSEMBLY NEEDS |
| | PRODUCT APPROVALS & SIGNED & SEALED |
| | DETAILS SHOWING INSTALLATION.THE |
| | MFGRS. SPECS OF THE SILICONE GEL NEEDS |
| | TO BE SUBMITTED. BEFORE C/O THE |
| | ENGINEEROR ARCHITECT MUST INSPECT THE |
| | BUTT GLASSASSEMBLY AND SIGN & SEAL A |
| | LETTER |
| | STATING IT HAS BE INSTALLED PER HIS |
| | SPECIFICATIONS. |
| | |
| | 6. NEED THE PRODUCT APPROVALS FOR THE |
| | STRUCTURAL COMPONANTS (SEE SAMPLE |
| | ATTACHED). |
| | |
| | ANY QUESTIONS PLEASE CALL: |
| | LEA SMITH,, BUILDING PLANS EXAMINER |
| | 805-6713 |