| 2004-02-24 00:00:00 | ****CORRECTIONS**** |
| | |
| | SAMANTHA HILL, BUILDING PLANS EXAMINER |
| | [email protected] |
| | |
| | 1.)SEE PREVIOUS LIST, ITEM #1, PROVIDE |
| | A SURVEY FOR THIS JOB. |
| | |
| | 2.)A NOTICE OF COMMENCEMENT MUST BE |
| | FILED WITH THE CLERK OF COURTS BEFORE A |
| | PERMIT CAN BE ISSUED. |
| | |
| | 3.)IMPACT FEES MUST BE PAID TO PALM |
| | BEACH COUNTY.THE PLANS MUST BE STAMPED |
| | AND THE RECEIPT ATTACHED TO THE |
| | APPLICATION. |
| | |
| | 4.)THE ENGINEER IS TO DATE THE SEAL, |
| | FAC61G-23.002. |
| | |
| | 5.)ADDITIONAL FEES DUE (VALUE |
| | INCREASE), $660.11.BZ235302 |
| | |
| | 6.)SEE PREVIOUS LIST, ITEM 6, STILL |
| | REFERS TO SBC, BUT NOW THE SHEET IS A15. |
| | |
| | 7.)SEE PREVIOUS LIST, ITEM #9.DESIGN |
| | IS FOR A SIMPLE DIAPHRAGM WHICH SHOULD |
| | BE SYMMETRICAL.THIS STRUCTURE IS NOT |
| | SYMMETRICAL.ADDRESS. |
| | |
| | 8.)PROVIDE A DETAIL FOR THE TRAY |
| | CEILING INCLUDING FIREBLOCKING. |
| | |
| | 9.)SEE PREVIOUS LIST, ITEM #13, |
| | PROVIDE A GUARDRAIL DETAIL TO COMPLY |
| | WITH FBC1608.2.2 AND FBC1015. |
| | |
| | 10.)STAIR RAIL IS TO COMPLY WITH |
| | FBC1608 AND 1007. |
| | |
| | 11.)SEE PREVIOUS LIST, PROVIDE A SOILS |
| | INVESTIGATION REPORT. |
| | |
| | 12.)SEE PREVIOUS LIST, ITEM #18, IN |
| | REGARDS TO WALL SECTIONS TO COMPLY WITH |
| | FBC1804.1.3 AND FBC1804.1.7 CITY OF |
| | WEST PALM BEACH AMENDMENTS. |
| | |
| | 13.)SEE PREVIOUS LIST, ITEM #21, |
| | PROVIDE STATEWIDE PRODUCT APPROVALS IN |
| | ADDITION TO THE TEST REPORTS PROVIDED. |
| | |
| | 14.)SEE PREVIOUS LIST, ITEM #27, |
| | STUCCO IS REQUIRED TO BE 7/8"VERTICAL |
| | APPLICATION, FBC2504.2.2, ASTM C926. |
| | THIS APPEARS IN SEVERAL PLACES; CHECK |
| | ALL DETAILS. |
| | |
| | 15.)PROVIDE MULLION PRODUCT APPROVALS, |
| | AS WELL AS ANY OTHER PRODUCT APPROVALS |
| | REQUIRED.ANY PRODUCT APPROVALS |
| | REQUIRED BUT NOT SUBMITTED WILL REQUIRE |
| | SEPARATE PERMITS. |
| | |
| | 16.)THERE ARE TWO 2-STORY WALL |
| | SECTIONS, ONE BLOCK AND ONE FRAME ON |
| | THE 2ND FLOOR.IT APPEARS THAT THE |
| | 2ND FLOOR IS TO BE FRAME (FLOOR PLAN), |
| | BUT THE HURRICANE SHUTTER SCHEDULE |
| | INDICATES BLOCK FASTENING FOR ALL |
| | OPENINGS.PLEASE CLARIFY. |
| | |
| | 17.)STORM SHUTTER PRODUCT APPROVAL IS |
| | ILLEGIBLE. |
| | |
| | 18.)WHEN RESUBMITTING, REPLACE SHEETS |
| | WHICH HAVE CHANGED AND SUBMIT OLD |
| | SHEETS SEPARATELY.INCLUDE A |
| | TRANSMITTAL LETTER INDICATING HOW EACH |
| | ITEM WAS ADDRESSED TO EXPEDITE PLAN |
| | REVIEW. |