| 2003-12-24 00:00:00 | DENIED |
| | REFERENCE: FBC-2001 PLUMBING |
| | FBC-2001 CHAPTER 1 |
| | FBC-2001 CHAPTER 11 |
| | FHA-98 DESIGN MANUAL |
| | |
| | 1) SPECIFICATION "A" OR"B" SHALL BE IN- |
| | DICATED ON PLANS PER REQUIREMENT 7B OF |
| | THE FHA DESIGN MANUAL. - RESPONSE NOTED, |
| | BUT NOT REVISED SHEET AP/A5.04 FOUND. |
| | 2) SHTS AP/P14.02 & AP/P14.04 CLEANOUTS |
| | SHALL BE LOCATED IN THE BREEZEWAYS IN |
| | ORDER TO COMPLY WITH SECTION 708.3.2 |
| | LOCATED NOT MORE THAN 100' APART. 2 WAY |
| | CLEANOUT WILL WORK. |
| | 3) SHT AP/P1404 THE DISCHARGE PIPE SHALL |
| | NOT HAVE ANY TRAPPED SECTIONS AND SHALL |
| | HAVE A VISIBLE AIR GAP OR AIR GAP FITT- |
| | ING LOCATED IN THE SAME ROOM AS THE |
| | WATER HEATER. RESPONSE STATES T & P TO |
| | DISCHARGE INTO DRAIN PAN BUT RELIEF |
| | VALVE PIPING DIAGRAM STILL SHOWS T&P |
| | PIPED UNDER SLAB. PLEASE CLAIRFY. SEC. |
| | 504.7.1 |
| | 4) AN RPZ BACKFLOW IS REQUIRED FOR EACH |
| | BUILDING. RESPONSE NOTED, BUT SHOW ON |
| | PLANS AS TYPICAL FOR EACH BLDG ON THE |
| | INLET OF BLDG. FOR REFERENCE. |
| | 5) SHT AP/P14.01 WATER RISER DIAGRAMS, |
| | THE WATER HAMMER ARRESTORS ARE STILL |
| | SHOWN IN CEILING. SHOW WATER HAMMER |
| | ARRESTORS NEAR THE FIXTURES AS REQUIRED |
| | BY PDI-WH 201 AND MANUF. INSTALL. INSTR. |
| | 6) SEE ATTACHED SHEET CONCERNING FS |
| | 533.80(2)(B) DESIGN PROFESSIONAL DOC- |
| | UMENTS. |
| | |
| | REVIEW BY KEN STEVENS |
| | (561) 805-6721 |
| | FAX (561) 653-2692 |
| | E-MAIL [email protected] |