| 2003-10-22 00:00:00 | FBC 1804.1.3 REQUIRES THE BOTTOM OF |
| | FOUNDATIONS TO BE AT LEAST 12" BELOW |
| | GRADE. SHEET 4 OF 4 OF THE RESUN |
| | LEASING/BODZIAK PLANS SHOWS THE PIERS |
| | ON TOP OF GRADE. PLEASE REVISE AS |
| | NECESSARY. |
| | |
| | ALSO, SHOW THE TOPOGRAPHY TO PROVIDE |
| | THESLOPING DRAINAGE IN ACCORDANCE WITH |
| | FBC 1804.1.7. |
| | |
| | SHOW THE METHOD OF TERMITE PROTECTION |
| | AS REQUIRED BY FBC 1816. |
| | |
| | SHEETS 1 AND 2 OF 6 ARE MISSING FROM |
| | THEEDUARDO VAZQUEZ, PE PLANS. |
| | |
| | SHEET 3 OF 6 OF THE VAZQUEZ PLANS SHOWS |
| | STRUCTURAL ALTERATIONS TO THE EXTERIOR |
| | WALLS OF THE BUILDING THAT WILL |
| | INVALIDATE THE DCA INSIGNIA AND MANDATE |
| | COMPLIANCE WITH THE CURRENT FBC. |
| | |
| | GIVEN THE ABOVE, PROVIDE DETAILS FOR |
| | THEINSTALLATION OF THE NEW DOORS AND |
| | WINDOWS, HURRICANE MISSLE IMPACT |
| | PROTECTION, AND TEST AND NOTICE OF |
| | ACCEPTANCE REPORTS.PROVIDE STRUCTURAL |
| | CALCULATIONS DEMONSTRATINGCOMPLIANCE |
| | WITH THE FBC FOR A 140 MPH WIND REGION. |
| | |
| | PROVIDE DETAILS FOR THE PLUMBING AND |
| | ELECTRICAL FOR THE NEW KITCHENETTE AREA |
| | AND THE ADDED PARTITIONS. |
| | |
| | THE FOLLOWING REGARDS THE PROPOSED |
| | PATIO, RAMP AND STAIR CONSTRUCTION. |
| | |
| | PLEASE PROVIDE STRUCTURAL CALCULATIONS |
| | FOR THE 2X2 GUARD RAIL AND 3/4" PICKETS |
| | SHOWN IN SECTIONS 4/P4 AND 5/P4.SEE |
| | FBC 1608.2 FOR MINIMUM DESIGN LOADS. |
| | |
| | SHOW THE STAIR TREAD AND RISER |
| | DIMENSIONS. SEE FBC 1007.2 AND 1007.3. |
| | |
| | HANDRAILS ARE REQUIRED ON BOTH SIDES OF |
| | STAIRS, EAST ELEVATION, FBC 1007.5.2 |
| | ANDWITHIN 30" OF EGRESS STAIR WIDTH, |
| | 1007. 5.7.PLEASE REVISE AS NECESSARY. |
| | |
| | SHEET 5 OF 6.PLEASE PROVIDE THE FIRE |
| | SPRINKLER DESIGN INFORMATION AS |
| | PROVIDED FOR IN NFPA 13-99 CHAPTER 8; |
| | AND CHAPTER 61G15-32 OF THE FL |
| | ADMINISTRATIVE CODE. |
| | |
| | THE DECLARED PERMIT VALUATION OF |
| | $20,000.00 IS TOO LOW FOR THE SCOPE OF |
| | WORK DECLARED ON SHEET 3 OF 6 OF THE |
| | VAZQUEZ PLANS.PLEASE PROVIDE A SIGNED |
| | CONTRACT(S) ANDDETAILED TAKEOFFS, |
| | INCLUDING EXTENSIONS, TO ESTABLISH THE |
| | ACTUAL COSTS OF THE WORK FOR THIS |
| | PERMIT. |