Plan Review Notes
Plan Review Notes For Permit 03080349
Permit Number 03080349
Review Stop P
Sequence Number 3
Notes
Date Text
2003-11-20 00:00:00 
  
  
  
 PASSED/PROVISO
  
 PASSED SUBJECT TO RESPONSE FROM RODNEY
 COMPO CONCERNING REQUIREMENT FOR A
 DILUTION TANK FOR CHEMICAL LAB.
 NO PLUMBING SHALL BE INSTALLED UNTILL A
 RESPONSE HAS BEEN ISSUED. IF A DILUTION
 TANK IS REQUIRED THAN A REVISION WILL BE
 REQUIRED WITH THE TANK INCLUDED.
  
 THE SERVICE SINK SHALL CONNECT DOWN-
 STREAM OF THE BATHROOM GROUP. SECTION
 909.1 - A REVISION WILL BE REQUIRED FOR
 THE RED LINE CORRECTION SHOWN ON THE
 SANITARY RISER DIAGRAM.