| Date |
Text |
| 2003-01-07 00:00:00 | FAILED: |
| | 1. PLEASE NOTE THAT A SEPARATE PERMIT |
| | APPICATION AND FEES FOR UNDERGROUND |
| | UTILITIES AND CIVIL SITE WORKS WIIL BE |
| | REQUIRED. |
| | 2. SIDEWALK, CURB AND GUTTERS AS |
| | REQUIRED BY THE PLANNING DEPARTMENT (SEE |
| | ATTACHED LETTER) AROUND THE PROPERTY, |
| | MUST BE SHOWN, PLEASE COORDINATE WITH |
| | CITY ENGINEER'S OFFICE FOR THE |
| | REQUIREMENTS. 659-8040 MR. RICHARD |
| | PITTMAN. |
| | 3. ALL DRIVEWAYS MUST BE CONSTRUCTED PER |
| | CITY' STANDARDS AND RQUIREMENTS. |
| | 4. A CLEAN OUT MUST BE INSTALLED IN |
| | SEWER LATERALS IF ONE IS NOT THERE, IT |
| | SHALL BE THE RESPONSIBILITY OF THE |
| | DEVELOPER/ENGINEER/DEVELOPER TO DESIGN |
| | AND INSTALL THE NEW INVERT ELEVATION FOR |
| | THE BUILDING LATERAL TO MACH OR BE |
| | HIGHER THAN THE EXISTING WHILE MAINTAIN- |
| | ING THE PLUMBING CODE REQUIREMENT FOR |
| | EFFLUENT PIPE FALL WITH MINIMUM OF THREE |
| | FEET COVER. IF THESE REQUIREMENTS CAN NO |
| | T BE MET, THE CITY MUST BE NOTIFIED |
| | PRIOR TO INSTALLATION.659-8040, 659-8079 |
| | 5. ALL BACKFLOW PREVENTERS AND |
| | CONNECTIONS TO CITY SERVICES MUST BE |
| | APPROVED BY PUBLIC UTILITIES ENGINEERING |
| | SERVICES DEPT. 659-8040 MR. MANNY |
| | GONZALEZ. |
| | IF ANY QUESTIONS PLEASE CONTACT 659-8096 |
| | EXT. 8492 MOHAMMAD R. AMINI |